Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
28/06/2021
|
Sir, Please conduct the joint is inspection of the site with the concerned Range Officer detailed in the Annexure enclosed. II. Upload DPR of the Project. III. Upload Layout Plan with the dimensions of the Project
|
|
2
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
30/09/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
09/10/2021
|
Shape of the project has been shown as Linear, which may kindly be corrected.
|
|
4
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
26/10/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
16/12/2021
|
Please update the proposal as per attachment
|
|
6
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
31/01/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
07/02/2022
|
Project has been shown to be located in a scheduled Area (Part I, S.No. J), Which needs to be cleare
|
|
8
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
10/02/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
14/02/2022
|
Sir, the case be returned back after updating it on Parivesh Portal as per the case of WSS Bella Wussan
|
|
10
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
16/02/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
05/03/2022
|
No KMZ File is uploaded please upload the KMZ File
|
|
12
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
09/03/2022
|
The correction have been made as per the instruction received
|
|
13
|
Nodal Officer
|
EDS
|
CF (Srinagar Circle)
|
18/05/2022
|
Please upload the requisite documents
|
|
14
|
CF (Srinagar Circle)
|
EDS
|
DFO (Sindh Forest Division)
|
24/05/2022
|
For necessary action as desired by the Nodal Officer, FCA
|
|
15
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
26/05/2022
|
For necessary action as desired by the Nodal Officer, FCA
|
|
16
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
18/08/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Sindh Forest Division)
|
EDS
|
User Agency (pherwsd@gmail.com)
|
20/08/2022
|
please make the correction as per the EDS raised on 26-05-2022
|
|
18
|
User Agency (pherwsd@gmail.com)
|
REPLY
|
DFO (Sindh Forest Division)
|
20/08/2022
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Sindh Forest Division)
|
REPLY
|
CF (Srinagar Circle)
|
25/08/2022
|
The corrections have been made as per the instructions received
|
|
20
|
CF (Srinagar Circle)
|
EDS
|
DFO (Sindh Forest Division)
|
25/08/2022
|
Please upload requisite documents
|
|
21
|
DFO (Sindh Forest Division)
|
REPLY
|
CF (Srinagar Circle)
|
25/08/2022
|
The corrections have been made
|
|
22
|
CF (Srinagar Circle)
|
REPLY
|
Nodal Officer
|
26/08/2022
|
Sir, requisite information has been uploaded by the DFO Sindh Forest Division.
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
30/09/2022
|
EDS
|
|
24
|
Nodal Officer
|
EDS
|
CF (Srinagar Circle)
|
03/10/2022
|
Please upload the requisite documents as desired by Adm Deptt
|
|
25
|
CF (Srinagar Circle)
|
EDS
|
DFO (Sindh Forest Division)
|
07/10/2022
|
Area for CA Plan be corrected to 0.58 ha instead of 0.81 ha. 2. The amount against CA Plan be correctly reflected as 4.0845 lacs instead of 4.09 lacs in Part II.
|
|
26
|
DFO (Sindh Forest Division)
|
REPLY
|
CF (Srinagar Circle)
|
12/10/2022
|
The corrections have been made as per the instructions
|
|
27
|
CF (Srinagar Circle)
|
REPLY
|
Nodal Officer
|
13/10/2022
|
Requisite information has been updated in Form A Part-II.
|
|
28
|
Nodal Officer
|
REPLY
|
State secretary
|
27/10/2022
|
The requisite correction has been made by DFO Sindh
|
|