Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
25/01/2021
|
Joint Inspection
|
|
2
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
17/02/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
20/02/2021
|
Uploading/ submission of documents as desired in the EDS raised.
|
|
4
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
26/02/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
03/03/2021
|
Kindly upload the correct Layout Map.
|
|
6
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
03/03/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
12/03/2021
|
Kindly upload/ correct following detail in Form-A Part-I
1. Upload Approval of Project by the Competent Authority.
2. Authority letter issued on the name of Shri Rajinder Gupta whereas the person making application form is Shri Anil Gupta
3. Brief Note of the Project Covering main features of the Proposal, particularly its implication on environment / forest and mitigation measures like construction of retaining/ breast wall and no. of people to be benefited from the Project.
|
|
8
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
13/03/2021
|
The correction have been made as per the instruction received
|
|
9
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
19/03/2021
|
Please upload the requisite documents
|
|
10
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
20/03/2021
|
Please provide the requisite information letter.
|
|
11
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
22/03/2021
|
Kindly take necessary action as per the EDS enclosed
|
|
12
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
23/03/2021
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
09/04/2021
|
The correction have been made as per the instruction received
|
|
14
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
12/04/2021
|
Sir,
the necessary information has been uploaded.
|
|
15
|
State secretary
|
EDS
|
Nodal Officer
|
12/05/2021
|
EDS copy enclosed
|
|
16
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
12/05/2021
|
Please upload the requisite information as sought by the Administrative Department
|
|
17
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
12/05/2021
|
Proposal submitted for O ha diversion of Forest Land. Kindly verify and submit the proposal again as desired by the Adm. Department
|
|
18
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
14/06/2021
|
Kindly make the necessary corrections as desired by the higher authorities.
|
|
19
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
19/06/2021
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
22/06/2021
|
Necessary corrections have been made by the User Agency.
|
|
21
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
23/06/2021
|
Corrections have been made by the User Agency.
|
|
22
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
27/06/2021
|
please upload the enumeration list of trees/poles/saplings coming in the alignment of the proposed transmission line passing through forest within two days
|
|
23
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
29/06/2021
|
Resubmitted to Nodal officer.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
29/06/2021
|
The requisite documents/clarification has been submitted by user agency
|
|
25
|
State secretary
|
EDS
|
Nodal Officer
|
02/07/2021
|
EDs
|
|
26
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
03/07/2021
|
Kindly provide the requisite information within 3 days.
|
|
27
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
03/07/2021
|
Kindly provide the requisite information
|
|
28
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
05/07/2021
|
Kindly Upload/ correct the information as per EDS enclosed
|
|
29
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
06/07/2021
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
07/07/2021
|
Kindly make necessary corrections as per point No. A of EDS enclosed.
|
|
31
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
07/07/2021
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenmreudh@gmail.com)
|
07/07/2021
|
Kindly make necessary corrections as per point No. A of EDS enclosed earlier.
|
|
33
|
User Agency (xenmreudh@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
07/07/2021
|
The correction have been made as per the instruction received
|
|
34
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
07/07/2021
|
Necessary corrections have been made by the User Agency as per the EDS raised.
|
|
35
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
09/07/2021
|
Necessary corrections have been made as per EDS
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
09/07/2021
|
The requisite documents have been uploaded
|
|