  (i). Proposal No. : FP/JK/ROAD/65427/2020              (ii). Name of Project for which Forest Land is required : Upgradation and Maintenance of road from MRL01-Tarathpora to Waisa via Shenpora cherpawa Kulwari Lilam Stage -U ( Batch -I, 2019-20) Package No JK08-2012, Length = 8.5kms, Block Ramhal              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The road “Upgradation and maint. of road from MRL01-Tarathpora Wilgam to Waisa via Shenpora Cherpawa Kulwari Lilam stage-U , passes through number of habitations and on its completion shall benefit 11000 souls with better upgraded connectivity.Road of way proposed is 10m.              (iv). File no. : 9-JKB025-2021-CHA              (v). State : Jammu and Kashmir              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.184
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JK/ROAD/65427/202001/12/2020aa02/12/2020   15/12/2020 Kehmil Forest Division :15/12/2020North Circle Sopore:
  18/02/2021 (Kehmil Forest Division)

Jammu and Kashmir:
24/02/2021
Jammu and Kashmir:
25/02/2021
Jammu:
16/03/2021
16/04/2021
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Jammu and Kashmir) on:03/03/2021  
Replied by Nodal Officer (Jammu and Kashmir) on:04/03/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:24/02/2021  
Replied by Circle(North Circle Sopore) on:24/02/2021  
Query raised by Circle (North Circle Sopore) on:19/02/2021  
Replied by DFO (Kehmil Forest Division) on:24/02/2021  
Query raised by Circle (North Circle Sopore) on:24/02/2021  
Replied by DFO (Kehmil Forest Division) on:24/02/2021  
Query raised by DFO (Kehmil Forest Division) on:23/12/2020  
Replied by UA on :13/01/2021  
Query raised by DFO (Kehmil Forest Division) on:13/01/2021  
Replied by UA on :21/01/2021  
Query raised by DFO (Kehmil Forest Division) on:25/01/2021  
Replied by UA on :28/01/2021  
Query raised by DFO (Kehmil Forest Division) on:17/02/2021  
Replied by UA on :18/02/2021  
Query raised by DFO (Kehmil Forest Division) on:20/02/2021  
Replied by UA on :21/02/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .