Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
04/01/2021
|
Maps, Availability of non-forest land for CA, Muck dumping site, FRA certificate.
|
|
2
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
21/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
09/02/2021
|
EDS of Zaloora to Gujjarpat
|
|
4
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
09/02/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
12/02/2021
|
Variation in Area shown in Joint inspection report and online requisition made.
|
|
6
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
14/02/2021
|
The correction have been made as per the instruction received
|
|
7
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
16/02/2021
|
Please upload the requisite documents , enabling us to process the Proposal.
|
|
8
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
16/02/2021
|
EDS of Zaloora to Gujjarpati
|
|
9
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
16/02/2021
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
17/02/2021
|
Required documenti.e. signed check list submitted by DFO uploaded.
|
|
11
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
19/02/2021
|
Kindly upload the requisite information please.
|
|
12
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
20/02/2021
|
Kindly upload the requisite information as per attached EDS letter.
|
|
13
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
20/02/2021
|
EDS has been raised by the Nodal officer FCA wherein 4 Nos. of documents are shown pending and all the 4 documents are pending from the user agency. As such you are requested to go through the EDS and upload the necessary documents from your USER ID at the earliest so that the EDS is dropped and the case is considered on its merits please.
|
|
14
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
22/02/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
22/02/2021
|
Sir the corrections have been made as required by the Nodal Officer FCA.
|
|
16
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
23/02/2021
|
All requisite 04 documents uploaded as per EDS.Please check.
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
15/04/2021
|
EDS
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
17/04/2021
|
Please provide the requisite information as desired by MoEF&CC
|
|
19
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
19/04/2021
|
Please upload the requisite documents
|
|
20
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
19/04/2021
|
Please upload the requisite documents
|
|
21
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
20/04/2021
|
Kindly find attached the EDS raised by the Regional Office MOEF CC wherein S. No. 1,3,4 and 7 need to be cleared by the user agency.
|
|
22
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
23/04/2021
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
26/04/2021
|
Sir, the necessary corrections have been made, please check.
|
|
24
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
28/04/2021
|
The UA is once again advised to upload the DGPS map of project site with proper geo-coordinates, so that proposal can be processed.
|
|
25
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
28/04/2021
|
The UA is once again requested to upload the DGPS map of project site with proper geo-coordinates and not screen shot of KMZ file so that proposal can be processed
|
|
26
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
28/04/2021
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
28/04/2021
|
Sir, The correction have been made as per the instruction received by the user agency.
|
|
28
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
28/04/2021
|
Sir, the necessary corrections have been made by UA and DFO concerned, please check.
|
|
29
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
28/04/2021
|
Kindly ask the user agency to upload the KML file as sought by the IRO of both forest and non-forest portion
|
|
30
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
28/04/2021
|
Kindly upload the requisite KML file as sought by the IRO of both forest and non forest portion.
|
|
31
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (baramullapmgsy@gmail.com)
|
28/04/2021
|
Kindly upload the requisite KML file as sought by the IRO of both forest and non forest portion.
|
|
32
|
User Agency (baramullapmgsy@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
30/04/2021
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
30/04/2021
|
sir,
The correction have been made as per the instruction received.
|
|
34
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
30/04/2021
|
Sir, the KML file uploaded indicating both forest and non forest land, sir please check.
|
|
35
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
03/05/2021
|
As desired by IRO Jammu vide No. 9-JKB-029/2021-Jammu dated 15-04-2021 the area of C.A site may be increased to extent of 0.60 Ha. Revised proposal may accordingly be uploaded/submitted
|
|
36
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
06/05/2021
|
Please upload the updated CA proposal as desired by Nodal Officer FCA.
|
|
37
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
06/05/2021
|
Sir,
The revised CA has been prepared and uploaded as per guidelines and as such target plantation also got reduced and as such there is no additional need of vacant CA land.
Regards.
|
|
38
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
08/05/2021
|
Sir, as per Divisional Forest Officer, Kamraj Forest Division ''The revised CA has been prepared and uploaded as per guidelines and as such target plantation also got reduced and as such there is no additional need of vacant CA land.''
Sir, Please check.
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
08/05/2021
|
The requisite documents have been uploaded
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
11/05/2021
|
The requisite information has been uploaded by UA/DFO/Nodal officer
|
|