Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Reasi Forest Division)
|
14/12/2020
|
1. Upload the area calculation sheet of proposed area under diversion
|
|
2
|
DFO (Reasi Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
15/12/2020
|
The correction has been uploaded as per instructions received
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
18/03/2021
|
eds
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
24/03/2021
|
Please provide the requisite information
|
|
5
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
25/03/2021
|
Kindly upload the requisite information please.
|
|
6
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Reasi Forest Division)
|
25/03/2021
|
please upload the requisite documents
|
|
7
|
DFO (Reasi Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
31/03/2021
|
please upload the requisite documents
|
|
8
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Reasi Forest Division)
|
05/04/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Reasi Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
08/04/2021
|
The correction have been made as per the instruction received
|
|
10
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
10/04/2021
|
The requisite documents have been uplaoded.
|
|
11
|
Nodal Officer
|
REPLY
|
State secretary
|
12/04/2021
|
The requisite information has been uploaded.
|
|
12
|
State secretary
|
REPLY
|
Regional Office
|
13/04/2021
|
The requisite documents in response to the observations have been uploaded by the user agecny/DFO/Nodal Officer
|
|