Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
03/12/2020
|
The information required to be submitted for further processing of the case.
|
|
2
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
11/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
22/01/2021
|
Signature pending for Joint Inspection Report
|
|
4
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
26/01/2021
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
16/02/2021
|
Kindly upload the time period required for the project in Form-A.
|
|
6
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
16/02/2021
|
Kindly upload the time period required for the project in Form-A.
|
|
7
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
16/02/2021
|
Kindly upload the time period required for the project in Form-A.
|
|
8
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
16/02/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
16/02/2021
|
The correction has been made by the User Agency.
|
|
10
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
16/02/2021
|
The correction has been made by the User Agency.
|
|
11
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
18/02/2021
|
Kindly ask the User Agency to reconsider the proposal, so as to minimize the loss to the forest.
|
|
12
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
18/02/2021
|
Kindly ask the User Agency to reconsider the proposal, so as to minimize the loss to the forest.
|
|
13
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
18/02/2021
|
Necessary correction in the eds is required to be fulfilled by the user agency
|
|
14
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
26/02/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
26/02/2021
|
The justification certificate has been uploaded by he user agency for consideration please.
|
|
16
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
04/03/2021
|
Necessary corrections have been made by user agency and DFO.
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
22/03/2021
|
Please clarify
|
|
18
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
24/03/2021
|
Please upload the requisite information
|
|
19
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
24/03/2021
|
Please upload the requisite documents
|
|
20
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
24/03/2021
|
sir the necessary correction has been made
|
|
21
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
25/03/2021
|
The requisite information/clarification has been submitted
|
|
22
|
Nodal Officer
|
REPLY
|
State secretary
|
25/03/2021
|
The requisite information/clarification has been uploaded.
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
10/05/2021
|
EDS
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
11/05/2021
|
EDS
|
|
25
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
11/05/2021
|
Please upload the requisite documents
|
|
26
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
17/05/2021
|
Please upload the requisite documents
|
|
27
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
17/05/2021
|
Please upload the requisite documents
|
|
28
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
19/05/2021
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
25/05/2021
|
correct the requisite documents
|
|
30
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
25/05/2021
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
25/05/2021
|
correct please
|
|
32
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
25/05/2021
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
01/06/2021
|
Sir the Approved CA Plan has been uploaded. Hence submitted for further processing sir please.
|
|
34
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
02/06/2021
|
Necessary corrections have been made by and DFO.
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
03/06/2021
|
The requisite documents have been uploaded
|
|
36
|
State secretary
|
REPLY
|
Regional Office
|
04/06/2021
|
The requisite documents in response to the observations have been uploaded by the user agency/DFO Mahore.
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
28/06/2021
|
EDS
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
29/06/2021
|
EDS
|
|
39
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
29/06/2021
|
The CF/DFO/User Agency are requested to see the minutes of the REC held on 17-18/06/2021 and further upload the requisite documents /information.
|
|
40
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
30/06/2021
|
Please do the needful
|
|
41
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
30/06/2021
|
Please do the necessary corrections
|
|
42
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
12/07/2021
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
27/07/2021
|
please correct the information required
|
|
44
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
28/07/2021
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
28/07/2021
|
sir the user agency has corrected the KMZ file clearly mentioning all the dumping points. Hence submitted at your end sir please.
|
|
46
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
28/07/2021
|
The requisite documents have been uploaded as per the decision of the REC
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
28/07/2021
|
The requisite information has been uploaded.
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
29/07/2021
|
The requisite information has been uploaded by Nodal officer (FCA)
|
|