Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
03/11/2020
|
Joint Inspection
|
|
2
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
18/11/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
07/12/2020
|
Joint Inspection and necessary important documents
|
|
4
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
17/12/2020
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
18/12/2020
|
To provide Site Treatment Plans of all 15 proposed Dumping sites alongwith Technical Clarification of the same.
|
|
6
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
20/01/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
22/01/2021
|
Submission of required documents
|
|
8
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
25/01/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
28/01/2021
|
Submission of pending document
|
|
10
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
29/01/2021
|
The correction have been made as per the instruction received
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
09/03/2021
|
eds
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
24/03/2021
|
Please provide the requisite information
|
|
13
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
25/03/2021
|
Kindly upload the requisite information please.
|
|
14
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
25/03/2021
|
Please upload the requisite information
|
|
15
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
26/03/2021
|
Kindly make necessary corrections as per the EDS enclosed.
|
|
16
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
09/04/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
09/04/2021
|
Corrections have been made as per instructions received.
|
|
18
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
09/04/2021
|
pls submit CA plan as per model CA Plan
|
|
19
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
10/04/2021
|
Corrections have been made as per instructions received.
|
|
20
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
12/04/2021
|
SIr,
The requisite information has been uploaded.
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
12/04/2021
|
The requisite information has been uploaded.
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
12/04/2021
|
Requisite documents in response to the observations have been uploaded
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
01/05/2021
|
For Compliance
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
04/05/2021
|
For compliance
|
|
25
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
04/05/2021
|
Please revise the proposals as per discussion held in the REC meeting held on 30-04-2021
|
|
26
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
08/05/2021
|
pls send revised proposal as asked
|
|
27
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (xenpmgsyreasi@gmail.com)
|
08/06/2021
|
Kindly submit Forest Right Act Certificate issued by Deputy Commissioner Udhampur.
|
|
28
|
User Agency (xenpmgsyreasi@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
22/06/2021
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
23/06/2021
|
Corrections have been made as per the instructions received
|
|
30
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
23/06/2021
|
Corrections have been made as per the instructions received
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
27/06/2021
|
The requisite documents have been uploaded by the DFO Uhampur as per the directions of the REC issued in its meeting held on 30-04-2021
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
29/06/2021
|
The requisite documents have been uploaded by the DFO Uhampur as per the directions of the REC issued in its meeting held on 30-04-2021
|
|