Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Social Forestry Division Ramban)
|
EDS
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
27/01/2021
|
Kindly provide the information/ documents as mentioned in the pdf file uploaded
|
|
2
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
REPLY
|
DFO (Social Forestry Division Ramban)
|
13/02/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Social Forestry Division Ramban)
|
20/02/2021
|
Kindly upload the signed checklist of all documents
|
|
4
|
DFO (Social Forestry Division Ramban)
|
REPLY
|
CF (Chenab Circle Doda)
|
20/02/2021
|
Sir the requisite information has been uploaded
|
|
5
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
23/02/2021
|
Kindly upload the requisite information please.
|
|
6
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Social Forestry Division Ramban)
|
23/02/2021
|
Kindly upload the requisite information please
|
|
7
|
DFO (Social Forestry Division Ramban)
|
EDS
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
23/02/2021
|
Kindly upload/provide the requisite documents as mentioned in the pdf
|
|
8
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
REPLY
|
DFO (Social Forestry Division Ramban)
|
25/02/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Social Forestry Division Ramban)
|
REPLY
|
CF (Chenab Circle Doda)
|
25/02/2021
|
Sir the requisite documents have been uploaded as additional information in Part II.
|
|
10
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
26/02/2021
|
Sir, the requisite documents have been uploaded as additional information in part-II
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
07/05/2021
|
EDS
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
11/05/2021
|
EDS
|
|
13
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
11/05/2021
|
Please upload the requisite documents
|
|
14
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Social Forestry Division Ramban)
|
12/05/2021
|
Kindly upload the requisite information please.
|
|
15
|
DFO (Social Forestry Division Ramban)
|
EDS
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
13/05/2021
|
Kindly upload the requisite information please
|
|
16
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
REPLY
|
DFO (Social Forestry Division Ramban)
|
14/05/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Social Forestry Division Ramban)
|
REPLY
|
CF (Chenab Circle Doda)
|
15/05/2021
|
Sir the requisite information has been uploaded as additional information in Part II.
|
|
18
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
17/05/2021
|
Sir, the requisite information has been uploaded in form-II
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
17/05/2021
|
The requisite documents have been uploaded
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
20/05/2021
|
The requisite documents in response to the observations have been uploaded by the User Agency/DFO/Nodal Officer
|
|