Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
03/12/2020
|
EDS raised for approval of project by competent authority
|
|
2
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
20/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
22/01/2021
|
Eds raised for want of certificate for minimum use of Forest Land, Signature in the Joint Inspection Report and Undertaking for payment of NPV and other components
|
|
4
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
26/01/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
11/02/2021
|
Minimum use of forest land and other certificates not as per format
|
|
6
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
15/02/2021
|
The correction have been made as per the instruction received
|
|
7
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
19/02/2021
|
Please upload the total period for which the forest land is proposed to be diverted in the Part-I of form-A on PARIVESH portal
|
|
8
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
19/02/2021
|
Upload the detail of total period for which the forest land is proposed to be diverted on form-a of Part-I on PARIVESH portal
|
|
9
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
19/02/2021
|
Upload the detail of total period for which the forest land is proposed to be diverted on form-a of Part-I on PARIVESH portal
|
|
10
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
19/02/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
19/02/2021
|
The necessary information has been uploaded by the user agency
|
|
12
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
19/02/2021
|
The requisite documents have been uploaded
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
20/03/2021
|
Please update district profile.
|
|
14
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
22/03/2021
|
Please update district profile and ask the user agency to upload muck disposal plan as suggested vide Circular issued by this office
|
|
15
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
24/03/2021
|
Please update district profile and ask the user agency to upload muck disposal plan as suggested vide Circular issued by this office
|
|
16
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
24/03/2021
|
sir the district profile has been uploaded and muck disposal plan has already been uploaded by the user agency
|
|
17
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
24/03/2021
|
The requisite information has been uploaded
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
24/03/2021
|
District profile data has been updated
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
26/04/2021
|
EDS
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
28/04/2021
|
Please provide the requisite information as desired by MoEF&CC
|
|
21
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
28/04/2021
|
Kindly upload the requisite information please.
|
|
22
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
29/04/2021
|
upload the requisite documents
|
|
23
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
29/04/2021
|
please provide the requisite information so that the case can be processed further
1. detail for component wise breakup of forest land proposed for diversion.
2. Detailed MDP
3. Muck dumping yard as per joint survey are 08 in no. whereas as per muck disposal plan you have submitted 6 dumping yards.
4. Also KML of the project
|
|
24
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
18/05/2021
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
18/05/2021
|
Sir the necessary correction has been made. Hence submitted for for necessary action please.
|
|
26
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
19/05/2021
|
necessary correction has been made by DFO.
|
|
27
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
20/05/2021
|
Please upload the requisite documents
|
|
28
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
21/05/2021
|
Please upload the requisite documents
|
|
29
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
21/05/2021
|
please do the necessary correction
|
|
30
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
27/05/2021
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
01/06/2021
|
Sir the Approved CA Plan has been uploaded. Hence Submitted for further processing at your end sir please.
|
|
32
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
02/06/2021
|
necessary correction has been made by DFO.
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
03/06/2021
|
The requisite documents have been uploaded
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
04/06/2021
|
The requisite documents in response to the observations have been uploaded by the user agency/DFO mahore
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
28/06/2021
|
EDS
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
29/06/2021
|
EDS
|
|
37
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
29/06/2021
|
The CF/DFO/User Agency are requested to see the minutes of the REC held on 17-18/06/2021 and further upload the requisite documents /information.
|
|
38
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
30/06/2021
|
Please do the needful
|
|
39
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
30/06/2021
|
Please do the necessary corrections
|
|
40
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
02/07/2021
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
02/07/2021
|
sir all the formalities have been completed both by the user agency and DFO Office. Hence submitted for further processing please.
|
|
42
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
02/07/2021
|
Sir
As per the decision of REC the muck generation sheet has been uploaded by to the user agency
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
05/07/2021
|
The necessary correction has been made.
|
|
44
|
State secretary
|
REPLY
|
Regional Office
|
06/07/2021
|
The necessary correction has been made.
|
|