| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
28/05/2020
|
Land Availability Certificate and Forest Rights Act Certificate
|
|
|
2
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
19/02/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
20/02/2021
|
Submit/ upload pending document as per EDS raised
|
|
|
4
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
14/03/2021
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
19/03/2021
|
Please provide the requisite information.
|
|
|
6
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
19/03/2021
|
Kindly submit the information as desired in the EDS attached.
|
|
|
7
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
20/03/2021
|
The correction have been made as per the instruction received
|
|
|
8
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
20/03/2021
|
The correction have been made as per the instructions received
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
30/03/2021
|
Kindly upload the requisite information please.
|
|
|
10
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
30/03/2021
|
Kindly upload the requisite information please.
|
|
|
11
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
02/04/2021
|
Kindly submit the information as per the EDS raised by the Nodal Officer FCA.
|
|
|
12
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
28/05/2021
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
13/06/2021
|
Kindly make necessary correction for Point No. 1 as per the EDS raised by the Nodal Officer vide letter No. PCCF/FCA/3306/6184-86 dated 30.03.2021.
|
|
|
14
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
14/06/2021
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
28/06/2021
|
Kindly make necessary correction for Point No. 2 as per the EDS raised by the Nodal Officer vide letter No. PCCF/FCA/3306/6184-86 dated 30.03.2021.
|
|
|
16
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
29/06/2021
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
29/06/2021
|
Necessary corrections have been made as per the directions received.
|
|
|
18
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
30/06/2021
|
corrections have been made as per EDS
|
|
|
19
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
23/07/2021
|
Please upload the requisite documents
|
|
|
20
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
24/07/2021
|
Please upload the requisite documents
|
|
|
21
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
24/07/2021
|
Kindly make necessary corrections as per EDS Enclosed
|
|
|
22
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
07/08/2021
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
09/08/2021
|
Kindly make necessary corrections as per the EDS raised vide letter No.2299-2301/FDU dated 09-08-2021.
|
|
|
24
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
10/08/2021
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
10/08/2021
|
Kindly make necessary corrections as per the EDS raised vide letter No.2299-2301/FDU dated 09-08-2021.
|
|
|
26
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
10/08/2021
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
10/08/2021
|
Corrections have been made by the User Agency as per the EDS raised by the Nodal Officer (FCA) vide No.PCCF/FCA/3306/1654-56 dated 23.07.2021.
|
|
|
28
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
10/08/2021
|
Corrections have been made as per EDS.
|
|
|
29
|
State secretary
|
EDS
|
Nodal Officer
|
09/09/2021
|
EDS
|
|
|
30
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
10/09/2021
|
Kindly ask the user agency to upload the reply in respect of point no. 1 of the EDS.
|
|
|
31
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
11/09/2021
|
Please provide the reply of EDS raised by Nodal Officer FCA.
|
|
|
32
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
17/09/2021
|
Kindly upload the reply of EDS raised by Nodal Officer FCA.
|
|
|
33
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
23/09/2021
|
The correction have been made as per the instruction received
|
|
|
34
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
25/09/2021
|
Necessary document regarding reply of EDS has been uploaded by the User Agency as Additional Document.
|
|
|
35
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
27/09/2021
|
Reply of EDS dated 09.09.2021 is not enclosed. Plz provide the requiste information.
|
|
|
36
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
28/09/2021
|
Kindly make necessary corrections as per the EDS raized by the Nodal Officer, copy attached
|
|
|
37
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
28/09/2021
|
The correction have been made as per the instruction received
|
|
|
38
|
DFO (Udhampur Forest Division)
|
EDS
|
User Agency (arungupta1506@gmail.com)
|
30/09/2021
|
As per the EDS received in the instant proposal, the 0.9875 ha of forest land
is being proposed for diversion in the project. but, the user agency has requested to Deputy
Commissioner udhampur vide letter dated 27.07.2020 to issue FRA certicate
for 0.8875 ha forests land for the project. This needs to be rectified and
same may be uploaded on portal.
|
|
|
39
|
User Agency (arungupta1506@gmail.com)
|
REPLY
|
DFO (Udhampur Forest Division)
|
10/10/2021
|
The correction have been made as per the instruction received
|
|
|
40
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
13/10/2021
|
Necessary corrections have been made by the User Agency as per the EDS raised by the Nodal Officer FCA.
|
|
|
41
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
21/10/2021
|
Requisite correction has been made by User Agency as per EDS.
2nd point of EDS pertains to Nodal Officer.
|
|
|
42
|
Nodal Officer
|
REPLY
|
State secretary
|
28/10/2021
|
The requisite information has been uploaded.
|
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
08/12/2021
|
EDS
|
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
09/12/2021
|
EDs
|
|
|
45
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
10/12/2021
|
Kindly upload the requisite information please.
|
|
|
46
|
CF (East Circle Jammu)
|
EDS
|
DFO (Udhampur Forest Division)
|
10/12/2021
|
Kindly provide the repy of EDS raised by IRO Jammu.
|
|
|
47
|
DFO (Udhampur Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
17/12/2021
|
Necessary Correction has been made as per the instruction received.
|
|
|
48
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
23/12/2021
|
Necessary correction has been made as per EDS.
|
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
24/12/2021
|
The requisite information has been uploaded.
|
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
24/12/2021
|
Needful done by Nodal officer FCA/DFO Udhampur
|
|