| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
10/07/2020
|
SIGNING JOINT SURVEY,ENUMERATION LISTS ETC
|
|
|
2
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
23/11/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
12/03/2022
|
Kindly upload the requisite information/documents please.
|
|
|
4
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
14/03/2022
|
Kindly upload requisite documents as per EDS with in two days positively.
|
|
|
5
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
15/03/2022
|
Upload the EDS documents
|
|
|
6
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
11/04/2022
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
11/04/2022
|
Sir
User Agency has made the change as per EDS
|
|
|
8
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
12/04/2022
|
The correction have been made as per EDS and submitted for further needful please.
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
27/04/2022
|
The detail of non-forest land under colun B.2.4 need to be given by the user agency
|
|
|
10
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
27/04/2022
|
The detail of non-forest land under colun B.2.4 need to be given
|
|
|
11
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
02/05/2022
|
The details of non forest area under column 2 4 needs to be uploaded
|
|
|
12
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
05/05/2022
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
08/05/2022
|
User agency has uploaded the requisite documents as per EDS
|
|
|
14
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
09/05/2022
|
The correction have been made as per EDS and submitted for further needful please.
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
20/05/2022
|
Please upload the requisite documents
|
|
|
16
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
21/05/2022
|
Kindly upload the requisite documents as per EDS.
|
|
|
17
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
23/05/2022
|
Made correction as per EDS
|
|
|
18
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
25/05/2022
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
28/05/2022
|
User Agency has been made change as per EDS
|
|
|
20
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
28/05/2022
|
The necessary correction have been made as per EDS and submitted for further needful please.
|
|
|
21
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
03/06/2022
|
Please upload the requisite documents
|
|
|
22
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
03/06/2022
|
As per EDS upload the requisite information
|
|
|
23
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
06/06/2022
|
As per EDS upload the requisite information
|
|
|
24
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
06/06/2022
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
07/06/2022
|
Employment generation certificate must be upload in additional information
|
|
|
26
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
07/06/2022
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
08/06/2022
|
User Agency has made change as per EDS
|
|
|
28
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
08/06/2022
|
The correction have been made as per EDS and submitted for further needful please.
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
20/06/2022
|
as four number of dumping sites have been proposed in forest area, the muck disposal plan with engineering measures and biological meausres required to be uploaded by user agency and DFO Rajouri
|
|
|
30
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
23/06/2022
|
As four number of dumping sites have been proposed in forest area, the muck disposal plan with engineering measures and biological meausres required to be uploaded by user agency and DFO Rajouri
|
|
|
31
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
25/06/2022
|
Please upload the Biological Measurements of dumping site
|
|
|
32
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
02/07/2022
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
04/07/2022
|
User Agency has made the change as per EDS
|
|
|
34
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
05/07/2022
|
The correction have been made as per EDS and submitted for further needful please.
|
|
|
35
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
08/07/2022
|
Please prepare and upload the muck disposal plan in terms of engineerng measures and biological measures as per circular issued copy attached.
|
|
|
36
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
12/07/2022
|
Kindly prepare and upload the muck disposal plan in terms of engineerng measures and biological measures as per circular.
|
|
|
37
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
13/07/2022
|
Upload the documents as per EDS
|
|
|
38
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
26/07/2022
|
The correction have been made as per the instruction received
|
|
|
39
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
26/07/2022
|
please upload the biological measurements
|
|
|
40
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
28/07/2022
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
29/07/2022
|
User Agency has made the change as per EDS
|
|
|
42
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
01/08/2022
|
The correction have been made as per EDS and submitted for further needful please.
|
|
|
43
|
State secretary
|
EDS
|
Nodal Officer
|
25/08/2022
|
The letter regarding issuance of FRA Certificate has been addressed to DDC Rajouri instead of District Collector.
|
|
|
44
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
26/08/2022
|
The Administrative Department has raised the follwoing EDS
The letter regarding issuance of FRA Certificate has been addressed to DDC Rajouri instead of District Collector. Please ask the user agency to do the needful
|
|
|
45
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
26/08/2022
|
The Administrative Department has raised the follwoing EDS The letter regarding issuance of FRA Certificate has been addressed to DDC Rajouri instead of District Collector. Please ask the user agency to do the needful.
|
|
|
46
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
27/08/2022
|
Kindly FRA letter be addressed to District Collector instead of Deputy Commissioner and same be uploaded on Parivesh Portal
|
|
|
47
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
02/09/2022
|
The correction have been made as per the instruction received
|
|
|
48
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
02/09/2022
|
User Agency has uploaded the FRA letter addressed to District Collector
|
|
|
49
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
06/09/2022
|
The correction have been made as per instruction received and submit for further needful please.
|
|
|
50
|
Nodal Officer
|
REPLY
|
State secretary
|
07/09/2022
|
FRA communciation addressed to District Collector Rajouri has been uploaded by user agency in Part1
|
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
25/10/2022
|
EDS
|
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
27/10/2022
|
EDS
|
|
|
53
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
29/10/2022
|
Please upload the requisite documents
|
|
|
54
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
31/10/2022
|
Kindly upload the requisite documents as per EDS please.
|
|
|
55
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
31/10/2022
|
Kindly upload the requisite documents
|
|
|
56
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
04/11/2022
|
The correction have been made as per the instruction received
|
|
|
57
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
15/11/2022
|
Reply submitted as per EDS and submitted for further needful please.
|
|
|
58
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
15/11/2022
|
Kindly mentioned document name in additional documents i.e Biological Measure.
|
|
|
59
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
15/11/2022
|
After needful correction case hence submitted for further processing please.
|
|
|
60
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
15/11/2022
|
The correction have been made as per EDS and submitted for further needful please.
|
|
|
61
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
21/11/2022
|
Kindly upload the requisite information please.
|
|
|
62
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Rajouri Forest Division)
|
22/11/2022
|
Kindly uplod the requisite document as per EDS please.
|
|
|
63
|
DFO (Rajouri Forest Division)
|
EDS
|
User Agency (cejmurnbpwd@gmail.com)
|
23/11/2022
|
Kindly upload requisite documents as per EDS.
|
|
|
64
|
User Agency (cejmurnbpwd@gmail.com)
|
REPLY
|
DFO (Rajouri Forest Division)
|
26/11/2022
|
The correction have been made as per the instruction received
|
|
|
65
|
DFO (Rajouri Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
26/11/2022
|
Correction has been made as per EDS raised please
|
|
|
66
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
28/11/2022
|
The correction have been made as per EDS and submitted for further needful please.
|
|
|
67
|
Nodal Officer
|
REPLY
|
State secretary
|
07/12/2022
|
The requisite documents have been uploaded
|
|
|
68
|
State secretary
|
EDS
|
Nodal Officer
|
09/12/2022
|
Please make correction in the reference from IRO Jammu and name of Forest Division.
|
|
|
69
|
Nodal Officer
|
REPLY
|
State secretary
|
10/12/2022
|
The needful done
|
|
|
70
|
State secretary
|
REPLY
|
Regional Office
|
12/12/2022
|
The requisite documents have been uploaded
|
|