TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JK/ROAD/156153/2022              (ii). Name of Project for which Forest Land is required : Construction of the road from Narore to Kainthgali under NABARD              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The road takes from km 7h of PMGSY link road (Tirshi to Narore) which is connected with Gandala Tirshi road at km 5th The Tirshi Gandala road is connected to km 8th of Sambal Gandala road which takes off from km 65th of NH-1A. The area covered by road is backward & remote corner of Tehsil Udhampur.              (iv). File no. : 9-JKB-051/2022-Jammu              (v). State : Jammu and Kashmir              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.109
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JK/ROAD/156153/202202/06/2022aa07/06/2022   11/06/2022 Udhampur Forest Division :12/06/2022East Circle Jammu:
  21/07/2022 (Udhampur Forest Division)

Jammu and Kashmir:
29/07/2022
Jammu and Kashmir:
06/08/2022
Jammu:
07/09/2022
12/10/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (East Circle Jammu) on:24/07/2022  
Replied by DFO (Udhampur Forest Division) on:28/07/2022  
Query raised by DFO (Udhampur Forest Division) on:16/06/2022  
Replied by UA on :15/07/2022  
Query raised by DFO (Udhampur Forest Division) on:15/07/2022  
Replied by UA on :18/07/2022  
Query raised by DFO (Udhampur Forest Division) on:19/07/2022  
Replied by UA on :19/07/2022  
Query raised by DFO (Udhampur Forest Division) on:19/07/2022  
Replied by UA on :19/07/2022  
Query raised by DFO (Udhampur Forest Division) on:25/07/2022  
Replied by UA on :27/07/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .