TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JK/ROAD/155313/2022              (ii). Name of Project for which Forest Land is required : Completion of balance work of Mandagali Koyli road km 4th onwards              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : the construction of this road shall benifit the people onlarge scale who are residing in far flung hilly area who have to travel the distance by foot and also improve the living standard of public and overall economy of the area shall be highly imroved by completionof balance work of mandagali koyli              (iv). File no. : 9-JKA-006/2023-Jammu              (v). State : Jammu and Kashmir              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.375
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JK/ROAD/155313/202225/06/202222/11/2022  08/08/2022  03/08/2022  02/08/2022  27/07/2022  18/07/2022  06/07/2022  02/07/2022   26/11/2022  13/10/2022  03/08/2022  03/08/2022  29/07/2022  25/07/2022  16/07/2022  06/07/2022   28/11/2022   03/12/2022 Rajouri Forest Division :05/12/2022West Circle Rajouri:
  24/12/2022 (Rajouri Forest Division)

Jammu and Kashmir:
03/01/2023
Jammu and Kashmir:
25/02/2023
Jammu:
23/03/2023
02/05/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Jammu) on:31/03/2023  
Replied by State Government(Jammu and Kashmir) on:28/04/2023  
Query raised by State Government (Jammu and Kashmir) on:05/04/2023  
Replied by Nodal Officer (Jammu and Kashmir) on:24/04/2023  
Query raised by Nodal Officer (Jammu and Kashmir) on:10/01/2023  
Replied by Circle(West Circle Rajouri) on:09/02/2023  
Query raised by Nodal Officer (Jammu and Kashmir) on:10/04/2023  
Replied by Circle(West Circle Rajouri) on:17/04/2023  
Query raised by Circle (West Circle Rajouri) on:10/01/2023  
Replied by DFO (Rajouri Forest Division) on:09/02/2023  
Query raised by Circle (West Circle Rajouri) on:11/04/2023  
Replied by DFO (Rajouri Forest Division) on:13/04/2023  
Query raised by DFO (Rajouri Forest Division) on:08/12/2022  
Replied by UA on :16/12/2022  
Query raised by DFO (Rajouri Forest Division) on:23/12/2022  
Replied by UA on :23/12/2022  
Query raised by DFO (Rajouri Forest Division) on:18/01/2023  
Replied by UA on :07/02/2023  
Query raised by DFO (Rajouri Forest Division) on:11/04/2023  
Replied by UA on :12/04/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .