Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bhaderwah Forest Division)
|
EDS
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
09/03/2022
|
kindly provide 4 sets Hardcopy of this project with seal and signature of Executive Engineer..
|
|
2
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
REPLY
|
DFO (Bhaderwah Forest Division)
|
11/03/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bhaderwah Forest Division)
|
EDS
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
12/03/2022
|
kindly Depute your filed functionary for joint inspection with Range Officer Kellar .
|
|
4
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
REPLY
|
DFO (Bhaderwah Forest Division)
|
21/04/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bhaderwah Forest Division)
|
EDS
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
26/04/2022
|
Kindy place a fresh indent
|
|
6
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
REPLY
|
DFO (Bhaderwah Forest Division)
|
10/05/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bhaderwah Forest Division)
|
EDS
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
11/05/2022
|
Kindly upload the Joint Inspection Letter
|
|
8
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
REPLY
|
DFO (Bhaderwah Forest Division)
|
06/06/2022
|
The correction have been made as per the instruction received
|
|
9
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
03/08/2022
|
Kindly upload the requisite information please.
|
|
10
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
04/08/2022
|
Kindly upload the requisite information please.
|
|
11
|
DFO (Bhaderwah Forest Division)
|
EDS
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
06/08/2022
|
Kindly upload the requisite information please.
|
|
12
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
REPLY
|
DFO (Bhaderwah Forest Division)
|
06/08/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
13/08/2022
|
The requisite documents has been uploaded
|
|
14
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
13/08/2022
|
Kindly upload the requisite information please.
|
|
15
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
13/08/2022
|
The requisite document has been uploaded
|
|
16
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
16/08/2022
|
Kindly upload the legible copy of the CA approval order.
|
|
17
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
20/08/2022
|
The requisite document has been uploaded
|
|
18
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
22/08/2022
|
Kindly upload the geo-coordinates please.
|
|
19
|
DFO (Bhaderwah Forest Division)
|
EDS
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
26/08/2022
|
You are requested for joint inspection with Forest Officials and submit the Joint Inspection Report for further necessary action
|
|
20
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
REPLY
|
DFO (Bhaderwah Forest Division)
|
26/08/2022
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
02/09/2022
|
The correction have been made as per the instruction received
|
|
22
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
07/09/2022
|
Sir, the desired information has been uploaded as per EDS.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
15/09/2022
|
Please upload the comments in light of report of DFO Bhaderwah
|
|
24
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
16/09/2022
|
Kindly upload the requisite information please.
|
|
25
|
DFO (Bhaderwah Forest Division)
|
EDS
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
19/09/2022
|
kindly submit the report as per EDS
|
|
26
|
User Agency (xenbhaderwahrnb66@gmail.com)
|
REPLY
|
DFO (Bhaderwah Forest Division)
|
29/09/2022
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
06/10/2022
|
The reply of EDS has been submitted by the user agency .
|
|
28
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
07/10/2022
|
Sir, the desired information has been uploaded by user agency as per EDS.
|
|
29
|
State secretary
|
EDS
|
Nodal Officer
|
12/11/2022
|
Please re-upload CA Toposheet and CA Geo Ref Map. Form-A Part II S. no 13 iii and iv
|
|
30
|
Nodal Officer
|
REPLY
|
State secretary
|
12/11/2022
|
Sir, Please use Mozilla Firefox Browser to open the proposal for S.No 13 Geo referenced map on Toposheet and DGPS
|
|
31
|
State secretary
|
EDS
|
Nodal Officer
|
14/11/2022
|
EDS
|
|
32
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
14/11/2022
|
Please upload the Part-II with correct amount of CA detail
|
|
33
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
17/11/2022
|
Please upload the Part-II with correct amount of CA detail
|
|
34
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
17/11/2022
|
The requisite correction has been made as per instruction....
|
|
35
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
18/11/2022
|
Sir, the desired information has been corrected and uploaded.
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
18/11/2022
|
revised Part-II format with correct amount of compebsatory outlay has been uplaoded in Part-II at sr. No. 64 (additional documents)
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
21/12/2022
|
EDS
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
21/12/2022
|
EDS
|
|
39
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
23/12/2022
|
Please upload the requisite documents
|
|
40
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
24/12/2022
|
Kindly upload the requisite information please.
|
|
41
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
03/02/2023
|
All Requisite information and document uploaded as per EDS
|
|
42
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
03/02/2023
|
Kindly upload the requisite information please.
|
|
43
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
03/02/2023
|
All Requisite information and document uploaded as per EDS
|
|
44
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
10/02/2023
|
All Requisite information and document uploaded as per EDS
|
|
45
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
20/02/2023
|
Kindly upload the requisite information please.
|
|
46
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Bhaderwah Forest Division)
|
20/02/2023
|
Kindly upload the requisite information please.
|
|
47
|
DFO (Bhaderwah Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
23/02/2023
|
As per Eds DFO is required to to submit impact mitigation plan for Leopard. as it is mentioned in Para 8 Column (I) that Leopard is occasional cited and no need to upload impact mitigation plan for Leopard
|
|
48
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
25/02/2023
|
As per Eds DFO is required to to submit impact mitigation plan for Leopard. as it is mentioned in Para 8 Column (I) that Leopard is occasional cited and no need to upload impact mitigation plan for leopard.
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
25/02/2023
|
Sir, The requisite information has been uploaded.
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
25/02/2023
|
The requisite information has been uploaded
|
|