Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
13/04/2022
|
Provide the document of Project approval copy from competent authority and FRA certificate
|
|
2
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
27/04/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
18/05/2022
|
The CA proposal is pending with DFO Teritorial concerned so it is requested your goodself to take up the issue with DFO Teritorial DODA for submission of CA proposal to DFO SF DODA at the earliest so as to furnished the case and uploaded on the parivesh portal
|
|
4
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
21/05/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
23/05/2022
|
Provide the document of FRA certificate for the settlement of Right under the Forest Right Act
|
|
6
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
23/05/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
23/05/2022
|
Please provide Project approval copy by the concerned ministry and sanction order No of finance department and provide FRA certificate issued by the Deputy Commissioner Doda
|
|
8
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
30/05/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
02/06/2022
|
Provide revised Check list
|
|
10
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
03/06/2022
|
The correction have been made as per the instruction received
|
|
11
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
29/06/2022
|
Please upload the requisite documents
|
|
12
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Social Forestry Division Doda)
|
29/06/2022
|
Kindly upload the requisite documents within two days positively.
|
|
13
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
30/06/2022
|
Under column B-2.3 in part-I the village breakup of forest and non forest land has not been given the detail of forest and non forest land to be filled by UA under column B-2. 3 make correction within a day
|
|
14
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
12/07/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Social Forestry Division Doda)
|
REPLY
|
CF (Chenab Circle Doda)
|
13/07/2022
|
The correction have been made as per the instruction received
|
|
16
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
14/07/2022
|
Sir, the desired information has been uploaded as per EDS.
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
08/08/2022
|
EDS
|
|
18
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
10/08/2022
|
Please upload the requisite documnents as desired by the Adm. Deptt
|
|
19
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Social Forestry Division Doda)
|
10/08/2022
|
Kindly upload the requisite information please.
|
|
20
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
10/08/2022
|
Proposal no. And Title of the Project which has not been mentioned on undertaking furnished by UA i.e undertaking of NPV, Addl. NPV AND CA etc. And mention on Joint Inspection Report please correct all documents mentioned proposal no. And Title of the project
|
|
21
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
12/08/2022
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Social Forestry Division Doda)
|
EDS
|
User Agency (xenrbddoda@gmail.com)
|
13/08/2022
|
Proposal No. and Title of the project has not mentioned in the Joint Site Inspection report by User Agency and Proposal No. and Title of the project has not mentioned in Certificate No Violation of forest conservation act 1980 please provide immediate these documents
|
|
23
|
User Agency (xenrbddoda@gmail.com)
|
REPLY
|
DFO (Social Forestry Division Doda)
|
18/08/2022
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Social Forestry Division Doda)
|
REPLY
|
CF (Chenab Circle Doda)
|
20/08/2022
|
Incorrect Proposal No. has been mentioned on Form A Part III by CF Chenab Circle On Site Inspection Report please correct FP/JK/ROAD/146385/2021 and all corrections have been made as per instruction received by SG
|
|
25
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
22/08/2022
|
Sir, the desired information has been corrected and uploaded as per the eds received.
|
|
26
|
Nodal Officer
|
REPLY
|
State secretary
|
24/08/2022
|
The requisite information has been uploaded.
|
|