Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
01/12/2021
|
Joint inspection date fixed on 07.12.2021 & upload requisite documents
|
|
2
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
15/12/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
15/12/2021
|
Please upload Joint verification report and other documents
|
|
4
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
17/12/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
18/12/2021
|
Upload Joint verification report as per format, KML file, Layout Plan and other documents including certificate for additional NPV
|
|
6
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
28/12/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
28/12/2021
|
Upload Joint verification report as per format, KML file, Layout Plan and other documents including certificate for additional NPV
|
|
8
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
02/01/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
08/01/2022
|
upload joint inspection report, KML file and other documents duly signed by DFO
|
|
10
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
23/02/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
24/02/2022
|
Upload separate documents
|
|
12
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
24/02/2022
|
The correction have been made as per the instruction received
|
|
13
|
CF (East Circle Jammu)
|
EDS
|
DFO (Ramnagar Forest Division)
|
03/03/2022
|
Please provide the requisite information as per EDS.
|
|
14
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
04/03/2022
|
Please upload requisite document as per EDS
|
|
15
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
07/03/2022
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (bdochanunta@gmail.com)
|
07/03/2022
|
Please upload FRA letter
|
|
17
|
User Agency (bdochanunta@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
07/03/2022
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Ramnagar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
07/03/2022
|
The correction has been made as per EDS
|
|