A. General Details
  (i). Proposal No. : FP/JK/ROAD/143554/2021              (ii). Name of Project for which Forest Land is required : Construction of road from Ramnagar to Basantgarh Phase- II (l= 11.0 Km )              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Ramnagar to Basantgarh road Phase II KM 21st to 31st              (iv). File no. : 9-JKB-094/2021-Jammu              (v). State : Jammu and Kashmir              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.982
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JK/ROAD/143554/202115/06/2021aa21/06/2021   29/06/2021 Ramnagar Forest Division :29/06/2021East Circle Jammu:
  02/09/2021 (Ramnagar Forest Division)

Jammu and Kashmir:
08/09/2021
Jammu and Kashmir:
04/12/2021
Jammu:
21/12/2021
24/01/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Jammu and Kashmir) on:14/09/2021  
Replied by Circle(East Circle Jammu) on:21/10/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:03/11/2021  
Replied by Circle(East Circle Jammu) on:26/11/2021  
Query raised by Circle (East Circle Jammu) on:04/09/2021  
Replied by DFO (Ramnagar Forest Division) on:06/09/2021  
Query raised by Circle (East Circle Jammu) on:15/09/2021  
Replied by DFO (Ramnagar Forest Division) on:16/10/2021  
Query raised by Circle (East Circle Jammu) on:06/11/2021  
Replied by DFO (Ramnagar Forest Division) on:26/11/2021  
Query raised by DFO (Ramnagar Forest Division) on:29/06/2021  
Replied by UA on :27/08/2021  
Query raised by DFO (Ramnagar Forest Division) on:27/08/2021  
Replied by UA on :27/08/2021  
Query raised by DFO (Ramnagar Forest Division) on:16/09/2021  
Replied by UA on :15/10/2021  
Query raised by DFO (Ramnagar Forest Division) on:12/11/2021  
Replied by UA on :23/11/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .