Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
28/07/2021
|
Kindly provide the details of Muck Plan to this office.
|
|
2
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
30/09/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
30/10/2021
|
The User Agency is requested to carry out a joint demarcation with Revenue and forest department tp ascertain the actual quantum of the Forest land coming in the proposed alignment of the Road. the case shall be further processed once the joint demarcation is done.
|
|
4
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
23/03/2022
|
The correction have been made as per the instruction received
|
|
5
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
24/03/2022
|
Please provide the requisite information as per EDS.
|
|
6
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
25/03/2022
|
Kindly find enclosed herewith the letter
|
|
7
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
26/03/2022
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
30/03/2022
|
Sir, as directed the correction has been made
|
|
9
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
31/03/2022
|
Please do the needful as correction is not made yet.
|
|
10
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
06/04/2022
|
The correction in KML area has not been made. Kindly do the needful
|
|
11
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
06/04/2022
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
07/04/2022
|
As requested kindly upload the documents
|
|
13
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
11/04/2022
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
12/04/2022
|
The correction has been made by the User Agency and the same has been uploaded on the portal
|
|
15
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
13/04/2022
|
Please provide the requisite information as per EDS.
|
|
16
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
25/04/2022
|
Kindly find enclosed herewith the attached file
|
|
17
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
28/05/2022
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
01/06/2022
|
Sir,kindly find enclosed herewith the attached file
|
|
19
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
02/06/2022
|
Kindly provide the requisite information as per EDS.
|
|
20
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
07/06/2022
|
Sir, Specific Recommendation as per format of Part-II, ( page no 22-24 of Handbook of forest (Conservation) Act,1980 and Forest Conservation Rules,2003 ( Guidelines & Clarification),2019 MoEF&CC; at S.No.16 of online Part-II has been uploaded in additional documents under S.No.13 of Part-II.
|
|
21
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
21/06/2022
|
The project area of non-forest land has been changed. The user agency may be advised to make necessary correction in rest of the components in Part-I
|
|
22
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
22/06/2022
|
Kindly make the necessary corrections as per the instructions conveyed by the Nodal Officer.
|
|
23
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
23/06/2022
|
The project area of non-forest land has been changed. The user agency are requested to make necessary correction in rest of the components in Part-I
|
|
24
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
18/07/2022
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
23/07/2022
|
sir, kindly find enclosed herewith the attachment
|
|
26
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
27/07/2022
|
As recommended by DFO, the case is submitted.
|
|
27
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
28/07/2022
|
There is involvement of 1.68 Ha of non-forest land, however under column 2.3, village wise breack up and under column 2.4 compotent wise break, non forest land of 3.48 Ha has been filled in Part 1 By the user agency. The correct detail of non-forest land need to be filled by the user agency
|
|
28
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
29/07/2022
|
There is involvement of 1.68 Ha of non-forest land, however under column 2.3, village wise breack up and under column 2.4 compotent wise break, non forest land of 3.48 Ha has been filled in Part 1 By the user agency. The correct detail of non-forest land need to be filled by the user agency
|
|
29
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (eediv2jmu@gmail.com)
|
30/07/2022
|
There is involvement of 1.68 Ha of non-forest land, however under column 2.3, village wise break up and under column 2.4 component wise break, non forest land of 3.48 Ha has been filled in Part 1 By the user agency. The correct detail of non-forest land need to be filled by the user agency
|
|
30
|
User Agency (eediv2jmu@gmail.com)
|
REPLY
|
DFO (Jammu Forest Division)
|
30/07/2022
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
01/08/2022
|
Sir, as directed the correction have been made by the user agency
|
|
32
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
01/08/2022
|
As directed, necessary correction have been made by the user agency
|
|
33
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
01/08/2022
|
Kindly upload the requisite information please.
|
|
34
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
02/08/2022
|
FRA certificate addressed to District Collector is uploaded at S.No. 4 of Additional Information Details under Checklist.
|
|
35
|
State secretary
|
EDS
|
Nodal Officer
|
24/08/2022
|
Please ask the user agency to upload the FRA certificate or a letter to the District Collector requesting for issuance of the same.
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
24/08/2022
|
The FRA communication has been uploaded by the user agency in Part I additional documents at Sr.No. 4, (Page No. 13)
|
|