Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
15/02/2021
|
Please upload the total period for which the proposed forest land to be diverted. approval of the project by the user agency, site suitability certificate for C.A. site
|
|
2
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Kishtwar Forest Division)
|
15/02/2021
|
Please upload the total time period for which the proposed forest land to be diverted, approval of the project by the user agency, site suitibiility certificate for the C. A project
|
|
3
|
DFO (Kishtwar Forest Division)
|
EDS
|
User Agency (xenpmgsykishtwar@rediffmail.com)
|
15/02/2021
|
Please upload the total time period for which the proposed forest land to be diverted, approval of the project by the user agency
|
|
4
|
User Agency (xenpmgsykishtwar@rediffmail.com)
|
REPLY
|
DFO (Kishtwar Forest Division)
|
15/02/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Kishtwar Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
18/02/2021
|
The requisite information has been uploaded
|
|
6
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
19/02/2021
|
reply of EDS raised by your good self
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
15/04/2021
|
EDS
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
17/04/2021
|
Please provide the requisite information as desired by MoEF&CC
|
|
9
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
19/04/2021
|
Please upload the requisite documents
|
|
10
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Kishtwar Forest Division)
|
19/04/2021
|
Kindly upload the requisite information please
|
|
11
|
DFO (Kishtwar Forest Division)
|
EDS
|
User Agency (xenpmgsykishtwar@rediffmail.com)
|
20/04/2021
|
EDS
|
|
12
|
User Agency (xenpmgsykishtwar@rediffmail.com)
|
REPLY
|
DFO (Kishtwar Forest Division)
|
24/04/2021
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Kishtwar Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
27/04/2021
|
The requisite documents have been uploaded
|
|
14
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
27/04/2021
|
Sir, the requisite documents have been uploaded.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
28/04/2021
|
Upload the requisite documents
|
|
16
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Kishtwar Forest Division)
|
29/04/2021
|
Kindly upload the requisite information please.
|
|
17
|
DFO (Kishtwar Forest Division)
|
EDS
|
User Agency (xenpmgsykishtwar@rediffmail.com)
|
29/04/2021
|
EDS
|
|
18
|
User Agency (xenpmgsykishtwar@rediffmail.com)
|
REPLY
|
DFO (Kishtwar Forest Division)
|
29/04/2021
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Kishtwar Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
29/04/2021
|
The correction has been made as per the instructions received.
|
|
20
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
30/04/2021
|
Sir, the desired information has been uploaded.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
03/05/2021
|
As desired by IRO Jammu vide No. dated 14-04-2021, the area of the C.A. site may be increased to the extent of 0.25 Ha. Revised proposal may accordingly be submitted/uploaded within two days.
|
|
22
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Kishtwar Forest Division)
|
03/05/2021
|
as desired by IRO Jammu vide No. dated 14-04-2021, the area of the C.A. site may be increased to the extent of 0.25 Ha. Revised proposal may accordingly be submitted/uploaded within one day.
|
|
23
|
DFO (Kishtwar Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
05/05/2021
|
The kml file CA has been uploaded
|
|
24
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
05/05/2021
|
Sir, the kml fila CA has been uploaded.
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
06/05/2021
|
The information has been uploaded.
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
11/05/2021
|
The reply has been uploaded by UA/DFO Marwah/Nodal Officer (FCA).
|
|