Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
06/12/2021
|
EDs with respect to FCA Proposal Diversion of under Ground forest land I/o Uri -1 Stage 11HE Project, Tehsil Uri Baramulla -FRA thereof
|
|
2
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
05/01/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
01/09/2022
|
EDs
|
|
4
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
17/10/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
26/02/2023
|
Eds for Uri I Stage II HE Project
|
|
6
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
03/03/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
08/05/2023
|
Eds for URI - I Stage II Project
|
|
8
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
08/05/2023
|
The correction have been made as per the instruction received
|
|
9
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
19/05/2023
|
Please do the necessary corrections
|
|
10
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
26/05/2023
|
EDs With respect to FCA Proposal Diversion of Uri -I Stage II HE Project, Tehsil Uri Baramulla
|
|
11
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
26/05/2023
|
The correction have been made as per the instruction received
|
|
12
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
26/05/2023
|
The correction has been made as per the instruction received
|
|
13
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
26/05/2023
|
Sir, please make necessary correction with respect to NPV on CA Scheme document.
|
|
14
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
27/05/2023
|
Sir,
the correction has been made as per the instruction received
|
|
15
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
29/05/2023
|
Covering letter uploaded by DFO at S.No. 1 in Additional Information Details need correction with respect to nomenclature of UA
|
|
16
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
29/05/2023
|
Sir, corrections done and submitted for futher necessary action please
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
17/06/2023
|
Please upload the requisite documents
|
|
18
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
19/06/2023
|
Divisional Forest Officer and User Agency are advised to do the necessary correction
|
|
19
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
10/07/2023
|
Please do the necessary corrections as per EDS.
|
|
20
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
13/09/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
19/09/2023
|
EDS cleared.
|
|
22
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
19/09/2023
|
Sir, the observations cleared and submitted for further necessary action.
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
26/09/2023
|
Please upload the requisite documents
|
|
24
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
29/09/2023
|
Please do the necessary corrections
|
|
25
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
29/09/2023
|
Please upload the required documents and do the necessary corrections
|
|
26
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
29/09/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
30/09/2023
|
Please upload the required NOC
|
|
28
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
30/09/2023
|
The correction have been made as per the instruction received
|
|
29
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
02/10/2023
|
The necessary corrections done and submitted for further action.
|
|
30
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
02/10/2023
|
Sir, documents uploaded and submitted
|
|
31
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
03/10/2023
|
Please correct the no. of years as 99 years instead of 100 years in Part-I.
Please upload the approval to CA Plan by the competent authority
|
|
32
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
03/10/2023
|
Please do the necessary coorections
|
|
33
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
03/10/2023
|
Please do the necessary correction.
|
|
34
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
03/10/2023
|
The correction have been made as per the instruction received
|
|
35
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
03/10/2023
|
Sir, corrections done.
|
|
36
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
03/10/2023
|
Sir, necessary corrections done by UA and DFO JV.
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
15/11/2023
|
EDS
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
21/11/2023
|
EDS
|
|
39
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
24/11/2023
|
Please upload the requisite documents
|
|
40
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
28/11/2023
|
Please do the corrections
|
|
41
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
29/11/2023
|
Please do the necessary correction.
|
|
42
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
29/11/2023
|
The correction have been made as per the instruction received
|
|
43
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
15/12/2023
|
Sir,
Please short note on emulative impact assessment and carrying capacity studies.
|
|
44
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
16/12/2023
|
The correction have been made as per the instruction received
|
|
45
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
19/12/2023
|
The correction have been made by this office as per the instructions received from DIGF (Central).
|
|
46
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
19/12/2023
|
Corrections done and submitted for further course of action.
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
11/01/2024
|
The requisite documents have been uploaded
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
15/01/2024
|
The requisite documents have been uploaded by Nodal Officer/DFO
|
|
49
|
Regional Office
|
EDS
|
State secretary
|
20/05/2024
|
EDS
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
22/05/2024
|
EDS
|
|
51
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
11/06/2024
|
Please upload the requisite documents
|
|
52
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
24/07/2024
|
Please upload the requisite documents
|
|
53
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
24/07/2024
|
Please upload the requisite documents
|
|
54
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
06/08/2024
|
The correction have been made as per the instruction received
|
|
55
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
06/08/2024
|
The correction have been made as per the instruction received.
|
|
56
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
06/08/2024
|
Sir, the corrections done.
|
|
57
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
12/09/2024
|
Please upload the reply/documents
|
|
58
|
CF (North Circle Sopore)
|
EDS
|
DFO (J.V.Forest Division)
|
13/09/2024
|
Please upload the reply/documents
|
|
59
|
DFO (J.V.Forest Division)
|
EDS
|
User Agency (uri1stageiienvironment@gmail.com)
|
25/09/2024
|
EDS raised by worthy Chief Conservator of Forests/ Nodal Officer FCA. Kindly upload the requisite information
|
|
60
|
User Agency (uri1stageiienvironment@gmail.com)
|
REPLY
|
DFO (J.V.Forest Division)
|
30/10/2024
|
The correction have been made as per the instruction received
|
|
61
|
DFO (J.V.Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
31/10/2024
|
The correction have been made by the User Agency as per the instructions received from Nodal officer vide his No PCCF/FCA/3386/ 233-36 dated 04-09-2024
|
|
62
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
02/11/2024
|
Please find attached document wrt the FCA proposal
|
|