TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JK/Approach/44582/2020              (ii). Name of Project for which Forest Land is required : 60 mtr single span major pmt bridge at chak nallah              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Acquisition of forest land for construction of Niru side approach for construction of 60.00 mtr single span major permanent bridge with psc girder type structure at km 7.525 over kishan ganga river on road Dawar-Niru-Baraub-Chakwali-Kaobul Gali under project beacn in Jammu and Kashmir state.              (iv). File no. : Fst/Land/Parivesh/38/2020              (v). State : Jammu and Kashmir              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.045
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/JK/Approach/44582/202015/02/202029/05/2020  18/02/2020  15/02/2020   29/05/2020  29/05/2020  16/02/2020   29/05/2020   24/07/2020 Bandipora Forest Division :27/07/2020Srinagar Circle:
  01/09/2020 (Bandipora Forest Division)

Jammu and Kashmir:
06/10/2020
Jammu and Kashmir:
12/11/2020
17/03/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Jammu and Kashmir) on:08/01/2021  
Replied by Nodal Officer (Jammu and Kashmir) on:01/03/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:14/10/2020  
Replied by Circle(Srinagar Circle) on:08/11/2020  
Query raised by Nodal Officer (Jammu and Kashmir) on:15/01/2021  
Replied by Circle(Srinagar Circle) on:25/02/2021  
Query raised by Circle (Srinagar Circle) on:04/09/2020  
Replied by DFO (Bandipora Forest Division) on:04/09/2020  
Query raised by Circle (Srinagar Circle) on:08/09/2020  
Replied by DFO (Bandipora Forest Division) on:14/09/2020  
Query raised by Circle (Srinagar Circle) on:23/09/2020  
Replied by DFO (Bandipora Forest Division) on:26/09/2020  
Query raised by Circle (Srinagar Circle) on:26/09/2020  
Replied by DFO (Bandipora Forest Division) on:29/09/2020  
Query raised by Circle (Srinagar Circle) on:16/10/2020  
Replied by DFO (Bandipora Forest Division) on:22/10/2020  
Query raised by Circle (Srinagar Circle) on:23/10/2020  
Replied by DFO (Bandipora Forest Division) on:29/10/2020  
Query raised by Circle (Srinagar Circle) on:16/01/2021  
Replied by DFO (Bandipora Forest Division) on:23/02/2021  
Query raised by Circle (Srinagar Circle) on:24/02/2021  
Replied by DFO (Bandipora Forest Division) on:24/02/2021  
Query raised by DFO (Bandipora Forest Division) on:29/07/2020  
Replied by UA on :28/08/2020  
Query raised by DFO (Bandipora Forest Division) on:11/09/2020  
Replied by UA on :14/09/2020  
Query raised by DFO (Bandipora Forest Division) on:18/01/2021  
Replied by UA on :20/01/2021  
Query raised by DFO (Bandipora Forest Division) on:21/01/2021  
Replied by UA on :06/02/2021  
Query raised by DFO (Bandipora Forest Division) on:06/02/2021  
Replied by UA on :08/02/2021  
Query raised by DFO (Bandipora Forest Division) on:12/02/2021  
Replied by UA on :16/02/2021  
NOTE:- Stage-I Approval accorded by : State Government .