TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JK/Approach/143480/2021              (ii). Name of Project for which Forest Land is required : Construction of 45 m span bridge over Gurai nallah              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 45 mtr span steel superstructure bridge over gurai nallah to replace the existing old hamilton bridge.              (iv). File no. : FST-Land/0FC/87/2021-02              (v). State : Jammu and Kashmir              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.25
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/JK/Approach/143480/202114/06/2021aa21/06/2021   25/06/2021 Bandipora Forest Division :26/06/2021Srinagar Circle:
  02/08/2021 (Bandipora Forest Division)

Jammu and Kashmir:
12/08/2021
Jammu and Kashmir:
04/09/2021
12/11/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Jammu and Kashmir) on:24/09/2021  
Replied by Nodal Officer (Jammu and Kashmir) on:18/10/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:24/08/2021  
Replied by Circle(Srinagar Circle) on:31/08/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:25/09/2021  
Replied by Circle(Srinagar Circle) on:06/10/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:06/10/2021  
Replied by Circle(Srinagar Circle) on:06/10/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:07/10/2021  
Replied by Circle(Srinagar Circle) on:08/10/2021  
Query raised by Circle (Srinagar Circle) on:05/08/2021  
Replied by DFO (Bandipora Forest Division) on:11/08/2021  
Query raised by Circle (Srinagar Circle) on:12/08/2021  
Replied by DFO (Bandipora Forest Division) on:12/08/2021  
Query raised by Circle (Srinagar Circle) on:24/08/2021  
Replied by DFO (Bandipora Forest Division) on:28/08/2021  
Query raised by Circle (Srinagar Circle) on:01/10/2021  
Replied by DFO (Bandipora Forest Division) on:05/10/2021  
Query raised by Circle (Srinagar Circle) on:08/10/2021  
Replied by DFO (Bandipora Forest Division) on:08/10/2021  
Query raised by DFO (Bandipora Forest Division) on:26/06/2021  
Replied by UA on :07/07/2021  
Query raised by DFO (Bandipora Forest Division) on:24/07/2021  
Replied by UA on :29/07/2021  
Query raised by DFO (Bandipora Forest Division) on:06/08/2021  
Replied by UA on :10/08/2021  
Query raised by DFO (Bandipora Forest Division) on:24/08/2021  
Replied by UA on :26/08/2021  
Query raised by DFO (Bandipora Forest Division) on:02/10/2021  
Replied by UA on :04/10/2021  
NOTE:- Stage-I Approval accorded by : State Government .