| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dharmdeomishra@gmail.com)
|
07/08/2020
|
Please reply attached Ltr. no. 1789 dt. 07.08.2020
|
|
|
2
|
User Agency (dharmdeomishra@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
25/08/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dharmdeomishra@gmail.com)
|
07/09/2021
|
Please reply attached Ltr. no. 2276 dt. 06-09-2021
|
|
|
4
|
User Agency (dharmdeomishra@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
05/05/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
20/07/2022
|
Reply of query raised by GoJ on four points has been.
|
|
|
6
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
01/08/2022
|
Please take note of EDS by GOJ.
|
|
|
7
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh East)
|
01/08/2022
|
Please take note of EDS by GOJ
|
|
|
8
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dharmdeomishra@gmail.com)
|
21/09/2022
|
Please reply attached Ltr. no. 2361dt. 30.08.2022
|
|
|
9
|
User Agency (dharmdeomishra@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
28/04/2023
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Hazaribagh East)
|
REPLY
|
CF (Hazaribagh)
|
03/05/2023
|
The correction have been made as per the instruction received.
|
|
|
11
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
03/05/2023
|
The correction have been made as per the instruction received.
|
|
|
12
|
Nodal Officer
|
REPLY
|
State secretary
|
04/05/2023
|
EDS Reply
|
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
01/06/2023
|
Some Quarry Raised
|
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
13/06/2023
|
Reply of query raised by GoI letter dated 01.06.2023 has been sought.
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
21/06/2023
|
Please take note on EDS by IRO, Ranchi
|
|
|
16
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh East)
|
22/06/2023
|
Please take note on EDS by IRO, Ranchi
|
|
|
17
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dharmdeomishra@gmail.com)
|
22/06/2023
|
Please do correction as per attached this office letter no. 1844 dated 22-06-2023
|
|
|
18
|
User Agency (dharmdeomishra@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
03/07/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Hazaribagh East)
|
REPLY
|
CF (Hazaribagh)
|
04/07/2023
|
The correction have been made as per the instruction received.
|
|
|
20
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
04/07/2023
|
The correction have been made as per the instruction received.
|
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
06/07/2023
|
EDS Reply
|
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
14/07/2023
|
Reply of query raised by GoI letter dated 01.06.2023 is being submitted.
|
|