TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/VELEC/40349/2019              (ii). Name of Project for which Forest Land is required : 33 KV VILL-PADMA TO VILL-NACHANVE, DDUGJY, HAZARIBAG              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : RURAL ELECTRIFICATION UNDER DEEN DAYAL UPADHYAY GRAM JYOTI YOJNA              (iv). File no. : FP/JH/VELEC/40349/2019              (v). State : Jharkhand              (vi). Category of the Project : Village Electricity              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 7.608
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JH/VELEC/40349/201921/05/201903/02/2020  04/09/2019  28/05/2019   06/02/2020  05/09/2019  29/08/2019   30/09/2019   10/01/2020 Hazaribagh West :10/02/2020Hazaribagh:
  24/06/2020 (Hazaribagh West)

Jharkhand:
18/07/2020
Jharkhand:
18/03/2021
Ranchi:
31/05/2021
17/01/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:22/06/2021  
Replied by State Government(Jharkhand) on:24/12/2021  
Query raised by State Government (Jharkhand) on:07/07/2021  
Replied by Nodal Officer (Jharkhand) on:25/10/2021  
Query raised by Nodal Officer (Jharkhand) on:27/08/2020  
Replied by Circle(Hazaribagh) on:26/02/2021  
Query raised by Nodal Officer (Jharkhand) on:13/07/2021  
Replied by Circle(Hazaribagh) on:04/10/2021  
Query raised by Circle (Hazaribagh) on:28/08/2020  
Replied by DFO (Hazaribagh West) on:22/02/2021  
Query raised by Circle (Hazaribagh) on:14/07/2021  
Replied by DFO (Hazaribagh West) on:24/09/2021  
Query raised by DFO (Hazaribagh West) on:02/03/2020  
Replied by UA on :02/06/2020  
Query raised by DFO (Hazaribagh West) on:01/09/2020  
Replied by UA on :13/02/2021  
Query raised by DFO (Hazaribagh West) on:22/07/2021  
Replied by UA on :07/08/2021  
Query raised by DFO (Hazaribagh West) on:17/08/2021  
Replied by UA on :31/08/2021  
Query raised by DFO (Hazaribagh West) on:13/09/2021  
Replied by UA on :20/09/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .