Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
17/10/2019
|
Please submit the compliance reports.
|
|
2
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
06/11/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
20/01/2020
|
Please submit the complince report
|
|
4
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
03/03/2020
|
The correction have been made as per the instruction received
|
|
5
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
12/06/2020
|
?????? ?????? ???? ???? ???? ?? ??? ???
|
|
6
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
12/06/2020
|
Correction has been done.
|
|
7
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
22/06/2020
|
Query raised by CCF, Bokaro vide letter no. 1026 dated 18-06-2020..
|
|
8
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
26/06/2020
|
Compliance has been done.
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
31/08/2020
|
Reply on query raised by GoJ on four points has been sought.
|
|
10
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
14/12/2020
|
Please take note on EDS by Nodal Officer
|
|
11
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
26/12/2020
|
Please submit a Query report soon.
|
|
12
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
11/01/2021
|
Letter No. 107 Dated 09.01.2021 has been attached.
|
|
13
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
11/01/2021
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
11/01/2021
|
Letter no.107 dated 09.01.2021 has been attached.
|
|
15
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
12/01/2021
|
Compliance has been done & letter no. 46 dated 12.01.2021 has attached.
|
|
16
|
Nodal Officer
|
REPLY
|
State secretary
|
30/03/2021
|
EDS Reply
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
22/06/2021
|
Some documents need to be uploaded.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
07/07/2021
|
Reply of query raised by IRO Ranchi letter dated 22.06.2021 has been sought.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
08/07/2021
|
Please take note of EDS by RO, Ranchi
|
|
20
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
14/07/2021
|
Please kindly provide the resolution report of the points raised by the Government of India, Regional Office, Ranchi without delay.
|
|
21
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
17/07/2021
|
Memo no. 1926 Dated 14.07.2021 has been attached.
|
|
22
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
20/07/2021
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
31/07/2021
|
Upload CA Land Undertaking
|
|
24
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
31/07/2021
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
05/08/2021
|
Rectify Tree enumeration list
|
|
26
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
05/08/2021
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
10/08/2021
|
Part-II Signed copy enclosed
|
|
28
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
26/08/2021
|
Compliance is incomplete, please complete the compliance.
|
|
29
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
27/08/2021
|
Letter no. 2414 Dated 27.08.2021 has been uploaded.
|
|
30
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
02/09/2021
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
06/09/2021
|
Letter no. 2493 Dated 04.09.2021 has been uploaded.
|
|
32
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
06/09/2021
|
Compliance Report on 7 points as PDF file is being submitted.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
29/09/2021
|
Please take note on EDS by Nodal officer
|
|
34
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
06/10/2021
|
Please submit the complete and point wise resolution report with all the annexures at the earliest, so that further action can be taken.
|
|
35
|
DFO (Bokaro)
|
EDS
|
User Agency (jusnldhn87forest@gmail.com)
|
21/10/2021
|
Memo no. 2899 Dated 21.10.2021 has been attached.
|
|
36
|
User Agency (jusnldhn87forest@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
13/11/2021
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
13/12/2021
|
Letter no 3439 Dated 11.12.2021 has been uploaded
|
|
38
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
20/12/2021
|
Please submit Hard Copy of Proposal Format Form-A Part-I
|
|
39
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
30/12/2021
|
Hardcopy of Proposal Format Form-A Part-I has been submitted.
|
|
40
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
31/12/2021
|
Compliance has been done vide letter no. 1004, dated 30.12.2021
|
|
41
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
31/12/2021
|
Online duly signed copy of part II with mentioning Name, Designation of the signing authority and date of signature is not uploaded as PDF file on the part DFO concerned, as additional information. Part II form is attached as PDF file.
|
|
42
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
31/12/2021
|
Kindly upload the scanned copy of Part-II as a additional information immediately.
|
|
43
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
31/12/2021
|
Part-II has been attached in Additional information.
|
|
44
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
01/01/2022
|
Compliance of the EDS raised on 31.12.2021 has been by DFO, Bokaro.
|
|
45
|
Nodal Officer
|
REPLY
|
State secretary
|
07/01/2022
|
EDS Reply
|
|
46
|
State secretary
|
REPLY
|
Regional Office
|
15/02/2022
|
Reply of query raised by GoI letter no. dated 22.06.2021 being submitted.
|
|