Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
09/10/2020
|
Letter no. 2170 dated 08.10.2020 is attached.
|
|
2
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
22/12/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
22/01/2021
|
Letter no. 260 Dated 22.01.2021 has been attached.
|
|
4
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
23/06/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
01/07/2021
|
Letter No. 1768 Dated 01.07.2021 has been uploaded.
|
|
6
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
29/07/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
26/08/2022
|
Letter no. 2402 Dt 26.08.2022 has been uploaded.
|
|
8
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
27/08/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
14/10/2022
|
Letter no. 2868 Dt 12.10.2022 has been attached.
|
|
10
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
18/11/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
06/12/2022
|
Letter no. 3359 Dt 06.12.2022 has been attached.
|
|
12
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
15/12/2022
|
The correction have been made as per the instruction received
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
26/04/2023
|
Reply of query raised by GoJ letter dated 24.04.2023 on two points has been sought.
|
|
14
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
03/05/2023
|
Please take note on EDS by GOJ
|
|
15
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
10/05/2023
|
It is requested to kindly provide the records/remarks on the points mentioned in the letter as soon as possible.
|
|
16
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
20/05/2023
|
Memo no. 1184 Dated 17.05.2023 has been attached.
|
|
17
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
06/06/2024
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
13/07/2024
|
Letter no. 1449 Dated 13.07.2024 has been attached.
|
|
19
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
18/07/2024
|
Compliance has been done.
|
|
20
|
Nodal Officer
|
REPLY
|
State secretary
|
27/07/2024
|
EDS Reply
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
19/09/2024
|
some query raised
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
24/10/2024
|
Reply of query letter date-17.09.2024 has been sought.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
30/10/2024
|
Please take note on EDS by GOI
|
|
24
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
11/11/2024
|
It is requested to submit the resolution report of the questioned points soon.
|
|
25
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
21/11/2024
|
Memo no. 2375 Dt 16.11.2024 has been attached.
|
|
26
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
24/12/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Bokaro)
|
EDS
|
User Agency (sdetsc3panchet@gmail.com)
|
18/01/2025
|
Letter no. 97 Dated 18.01.2025 has been attached.
|
|
28
|
User Agency (sdetsc3panchet@gmail.com)
|
REPLY
|
DFO (Bokaro)
|
01/02/2025
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
22/02/2025
|
Letter no. 295 Dated 22.02.2025 has been uploaded.
|
|
30
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
27/02/2025
|
Compliance has been done vide letter no. 233 dated 27.02.2025
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
25/03/2025
|
EDS Reply
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
29/04/2025
|
Reply of query letter date-17.09.2024 being submitted.
|
|