| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Simdega)
|
EDS
|
User Agency (jusnl.simdega@gmail.com)
|
01/08/2022
|
Proposal is not complete. please resubmit with all documents.
|
|
|
2
|
User Agency (jusnl.simdega@gmail.com)
|
REPLY
|
DFO (Simdega)
|
29/01/2025
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Gumla)
|
EDS
|
User Agency (jusnl.simdega@gmail.com)
|
07/03/2025
|
Please upload DFO authenticated land schedule.
|
|
|
4
|
User Agency (jusnl.simdega@gmail.com)
|
REPLY
|
DFO (Gumla)
|
29/11/2025
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Gumla)
|
EDS
|
User Agency (jusnl.simdega@gmail.com)
|
29/11/2025
|
1. Upload the DFO Authenticated LSD.
2. Upload the rectified KML as per DFO authenticated LSD.
|
|
|
6
|
User Agency (jusnl.simdega@gmail.com)
|
REPLY
|
DFO (Gumla)
|
08/12/2025
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Gumla)
|
EDS
|
User Agency (jusnl.simdega@gmail.com)
|
09/12/2025
|
The Uploaded KML file, and the corresponding cadastral sheets has area mismatch, wrong demarcation and irregularity. Please rectify it, to bring Land Schedule, KML File, Cadastral Sheets in sync.
|
|