Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Simdega)
|
EDS
|
User Agency (jusnl.kolebira@gmail.com)
|
11/03/2022
|
There are five document not attached with proposal copy. vide letter no.-734, dt. 10.03.2022. Please Compile & Correct it.
|
|
2
|
User Agency (jusnl.kolebira@gmail.com)
|
REPLY
|
DFO (Simdega)
|
18/03/2024
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Simdega)
|
EDS
|
User Agency (jusnl.kolebira@gmail.com)
|
10/04/2024
|
Following shortcomings were found in the said proposal-
1. Total area, forest land & JJ land proposed to be diverted is 22.6036 ha. but certificate pertaining to FRA has been provided only for 15.29977 ha.
2. Total Jungle-Jhari land proposed to be diverted is 16.6562 ha. but NOC for only 6.81 ha. has been provided by revenue department.
3. No Compensatory Afforestation land as required under the provision of FCA has been provided.
4. Site specific Wildlife Management Plan as required has not been submitted along with the proposal.
The above said shortcomings need to be complied for processing diversion proposal at the earliest.
|
|
4
|
User Agency (jusnl.kolebira@gmail.com)
|
REPLY
|
DFO (Simdega)
|
28/01/2025
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Simdega)
|
EDS
|
User Agency (jusnl.kolebira@gmail.com)
|
08/04/2025
|
1-Sutability certificate of CA land is not attached
|
|
6
|
User Agency (jusnl.kolebira@gmail.com)
|
REPLY
|
DFO (Simdega)
|
09/05/2025
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Simdega)
|
EDS
|
User Agency (jusnl.kolebira@gmail.com)
|
19/06/2025
|
Please submit authenticated land schedule
|
|