TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/TRANS/150631/2021              (ii). Name of Project for which Forest Land is required : 132 KV D/C Kolebira Simdega Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 132 KV D/C Kolebira Simdega Transmission Line              (iv). State : Jharkhand              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 22.6036
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JH/TRANS/150631/202129/12/202110/03/2022  04/03/2022  31/12/2021   10/03/2022  08/03/2022  12/01/2022   21/01/2022   02/03/2022 Simdega :11/03/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Simdega) on:11/03/2022  
Replied by UA on :18/03/2024  
Query raised by DFO (Simdega) on:10/04/2024  
Replied by UA on :28/01/2025  
Query raised by DFO (Simdega) on:08/04/2025  
Replied by UA on :09/05/2025  
Query raised by DFO (Simdega) on:19/06/2025  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by DFO .