  (i). Proposal No. : FP/JH/THE/41384/2019              (ii). Name of Project for which Forest Land is required : RESERVOIR & ASH DYKE OF NORTH KARANPURA SUPER THERMAL POWER PROJECT (3X660MW) IN DISTRICT CHATRA, JHARKHAND.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The present proposal is for a portion of land of 10.24 Ha area required for the construction of reservoir & Ash dyke to meet the project requirement. This portion of land was earlier identified for Garhi dam reservoir scheme of WRD, GoJh which is now cancelled and now the same has been allocated to              (iv). File no. : 8-76/2007-FC Vol.              (v). State : Jharkhand              (vi). Category of the Project : Thermal              (vii). Shape of forest land proposed to be diverted : Hybrid              (viii). Area of forest land proposed for diversion(in ha.): 10.24
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/JH/THE/41384/201930/07/201914/09/2019  07/08/2019   16/09/2019  28/08/2019   20/09/2019   28/11/2019 Chatra South :03/12/2019Chatra:
  12/06/2021 (Chatra South)

Jharkhand:
08/10/2021
Jharkhand:
22/10/2021
23/12/2021
HO Linked Date:
18/01/2022
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 02/02/2022  
Replied by State Government (Jharkhand) on:06/07/2022  
Query raised by MoEFCC,New Delhi on 18/08/2022  
Replied by State Government (Jharkhand) on:14/10/2022  
Query raised by State Government (Jharkhand) on:29/03/2022  
Replied by Nodal Officer (Jharkhand) on:19/05/2022  
Query raised by State Government (Jharkhand) on:02/09/2022  
Replied by Nodal Officer (Jharkhand) on:29/09/2022  
Query raised by Nodal Officer (Jharkhand) on:21/09/2022  
Replied by Circle(Chatra) on:24/09/2022  
Query raised by Circle (Chatra) on:29/07/2021  
Replied by DFO (Chatra South) on:17/08/2021  
Query raised by Circle (Chatra) on:31/08/2021  
Replied by DFO (Chatra South) on:28/09/2021  
Query raised by Circle (Chatra) on:22/09/2022  
Replied by DFO (Chatra South) on:23/09/2022  
Query raised by DFO (Chatra South) on:04/01/2020  
Replied by UA on :16/03/2020  
Query raised by DFO (Chatra South) on:09/05/2020  
Replied by UA on :20/08/2020  
Query raised by DFO (Chatra South) on:31/12/2020  
Replied by UA on :22/02/2021  
Query raised by DFO (Chatra South) on:02/08/2021  
Replied by UA on :11/08/2021  
Query raised by DFO (Chatra South) on:01/09/2021  
Replied by UA on :27/09/2021  
Query raised by DFO (Chatra South) on:22/09/2022  
Replied by UA on :22/09/2022  
NOTE:- Proposal has been : Rejected By FAC .