TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/ROAD/146250/2021              (ii). Name of Project for which Forest Land is required : Diversion of fresh Forest Land for development of Economic Corridors, Inter Corridors, Feeder Routes etc., under Bharatmala Pariyojana of Jaina More -Gola -Ormanjhi section in the state of Jharkhand.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project start from Km.21.110 and ends at Km. 81.450. Total stretch divided into two parts namely Jaina More to Gola (NH23) & Gola to Ormanjhi (NH320B). in case of NH23, it is start from Km.21.110 and ends at Km.55.650 & in case of NH320B, it is start from Km.55.650 and ends at Km.81.450 .              (iv). File no. : FP/JH/Road/146250/2021              (v). State : Jharkhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 99.7862
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/JH/ROAD/146250/202121/08/202108/12/2021  01/12/2021  23/11/2021  01/10/2021  23/09/2021  03/09/2021   08/12/2021  07/12/2021  30/11/2021  08/11/2021  29/09/2021  14/09/2021   09/12/2021   28/12/2021 Bokaro:  31/12/2021
Ramgarh:  31/12/2021
Ranchi:  31/12/2021
Bokaro:
  27/12/2022 (Bokaro)

Bokaro:
  28/12/2022 (Ramgarh)

Ranchi:
  05/12/2022 (Ranchi)

Jharkhand:
20/01/2023
Jharkhand:
02/03/2023
Ranchi:
04/05/2023
13/06/2023
By :Regional Office
Jharkhand
17/05/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Jharkhand) on:02/02/2023  
Replied by Circle(Ranchi) on:21/02/2023  
Query raised by Nodal Officer (Jharkhand) on:02/02/2023  
Replied by Circle(Bokaro) on:22/02/2023  
Query raised by Circle (Ranchi) on:02/01/2023  
Replied by DFO (Ranchi) on:17/01/2023  
Query raised by Circle (Bokaro) on:03/02/2023  
Replied by DFO (Bokaro) on:17/02/2023  
Query raised by Circle (Bokaro) on:03/02/2023  
Replied by DFO (Ramgarh) on:22/02/2023  
Query raised by DFO (Bokaro) on:07/01/2022  
Replied by UA on :15/10/2022  
Query raised by DFO (Ranchi) on:09/09/2022  
Replied by UA on :15/10/2022  
Query raised by DFO (Ramgarh) on:03/11/2022  
Replied by UA on :09/11/2022  
Query raised by DFO (Ramgarh) on:24/11/2022  
Replied by UA on :03/12/2022  
Query raised by DFO (Ramgarh) on:14/12/2022  
Replied by UA on :19/12/2022  
Query raised by DFO (Ranchi) on:07/01/2023  
Replied by UA on :08/01/2023  
Query raised by DFO (Ranchi) on:12/01/2023  
Replied by UA on :12/01/2023  
Query raised by DFO (Bokaro) on:07/02/2023  
Replied by UA on :10/02/2023  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Ranchi) on:30/05/2024  
Query raised by State Government (Jharkhand) on:27/06/2024  
Query raised by Nodal Officer on:03/07/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .