Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
05/01/2021
|
Please submit rectified proposal as per attached letter no. 71 dated 04.01.2020
|
|
2
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
13/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
10/03/2021
|
Please submit rectified proposal as per attached letter no. 755 dated 10.03.2021
|
|
4
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
12/04/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
08/06/2021
|
Please submit rectified proposal as per attached letter no. 1128 dated 31.05.2021
|
|
6
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
26/07/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
23/08/2021
|
Please do correction as per attached this office letter no. 2110 dated 21.08.2021
|
|
8
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
28/08/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
04/09/2021
|
Please do correction as per attached this office letter no. 2259 dated 03.09.2021
|
|
10
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
09/09/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
01/10/2021
|
Please do correction as per attached this office letter no. 2595 dated 01.10.2021
|
|
12
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
08/10/2021
|
The correction have been made as per the instruction received
|
|
13
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
07/12/2021
|
Please take note on EDS by Nodal Office.
|
|
14
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh East)
|
09/12/2021
|
Please take note on EDS by Nodal Office.
|
|
15
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
16/12/2021
|
Please take note on EDS by Nodal Office.
|
|
16
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
16/12/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Hazaribagh East)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
20/12/2021
|
Please do correction as per attached this office letter no. 3255 dated 20.12.2021
|
|
18
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh East)
|
23/12/2021
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Hazaribagh East)
|
REPLY
|
CF (Hazaribagh)
|
30/12/2021
|
The correction have been made as per the instruction received.
|
|
20
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
30/12/2021
|
The correction has been made as per the instruction received.
|
|