TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/RAIL/36506/2018              (ii). Name of Project for which Forest Land is required : Amrapali Railway Siding              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The application for diversion of Forest Land for 120.61 Ha is intended for construction of railway siding for evacuation of Coal. The alignment has been decided keeping in view the minimum disturbance to Forest land.The proposal includes construction of Railway siding, Silo, Belt conveyor, Culvert.              (iv). File no. : FP/JH/RAIL/36506/2028              (v). State : Jharkhand              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 120.61
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JH/RAIL/36506/201812/10/201818/07/2019  13/07/2019  10/07/2019  15/10/2018   19/07/2019  16/07/2019  12/07/2019  04/01/2019   23/01/2019   08/07/2019 Chatra South :19/07/2019Chatra:
  31/01/2023 (Chatra South)

Jharkhand:
11/02/2023
Jharkhand:
20/02/2023
Ranchi:
07/11/2023
18/01/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Jharkhand) on:05/04/2023  
Replied by Nodal Officer (Jharkhand) on:11/09/2023  
Query raised by Nodal Officer (Jharkhand) on:26/04/2023  
Replied by Circle(Chatra) on:28/08/2023  
Query raised by Circle (Chatra) on:08/05/2023  
Replied by DFO (Chatra South) on:21/08/2023  
Query raised by DFO (Chatra South) on:25/07/2019  
Replied by UA on :29/02/2020  
Query raised by DFO (Chatra South) on:09/05/2020  
Replied by UA on :15/06/2020  
Query raised by DFO (Chatra South) on:08/02/2021  
Replied by UA on :05/05/2021  
Query raised by DFO (Chatra South) on:27/07/2021  
Replied by UA on :30/11/2022  
Query raised by DFO (Chatra South) on:05/01/2023  
Replied by UA on :11/01/2023  
Query raised by DFO (Chatra South) on:11/05/2023  
Replied by UA on :17/08/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .