  (i). Proposal No. : FP/JH/RAIL/36382/2018              (ii). Name of Project for which Forest Land is required : Conducting Final Location Survey,Geotechnical Investigation,Design/Drawing Of Structure Between Biratoli & Tori For Rail Flyover At Tori And Biratoli To Mahuamilan              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Connection With Biratoli -Tori ROR( Flyover) Line Connection & Biratoli - Mahuamilan (Surface Line) Connection For Connectivity Of Three Line Of The New BG Line Between Tori & Shivpur.              (iv). File no. : FP/JH/Rail/36382/2018              (v). State : Jharkhand              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.537
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JH/RAIL/36382/201806/10/2018aa15/10/2018   29/10/2018 Latehar :29/10/2018Daltonganj:
  17/05/2019 (Latehar)

Jharkhand:
31/05/2019
Jharkhand:
25/06/2019
Ranchi:
02/08/2019
14/08/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Daltonganj) on:23/05/2019  
Replied by DFO (Latehar) on:25/05/2019  
Query raised by DFO (Latehar) on:31/10/2018  
Replied by UA on :03/01/2019  
Query raised by DFO (Latehar) on:03/01/2019  
Replied by UA on :05/01/2019  
Query raised by DFO (Latehar) on:11/01/2019  
Replied by UA on :29/01/2019  
Query raised by DFO (Latehar) on:31/01/2019  
Replied by UA on :28/02/2019  
Query raised by DFO (Latehar) on:01/03/2019  
Replied by UA on :17/04/2019  
Query raised by DFO (Latehar) on:22/04/2019  
Replied by UA on :14/05/2019  