Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
20/05/2016
|
queries sought in regard to correct land- schedule,topo- sheet,to submit cadastral maps, FRA NOC, GMJJ NOC, etc..
|
|
2
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
05/12/2017
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
08/12/2017
|
false uploading
|
|
4
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
29/01/2018
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
06/02/2018
|
certain documents are lacking such as marking of alignment in cadastral map, complete land schedule etc.
|
|
6
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
22/03/2018
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
29/03/2018
|
incomplete proposal. queries raised for compliance.
|
|
8
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
13/04/2018
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
19/05/2018
|
queries raised for compliance.
|
|
10
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
06/07/2018
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
26/07/2018
|
queries raised for compliance.
|
|
12
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
03/08/2018
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
08/08/2018
|
queries sought in regard to correct area of land.
|
|
14
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
09/08/2018
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
31/08/2018
|
incomplete proposal. queries raised for compliance.
|
|
16
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
13/09/2018
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
16/09/2018
|
incomplete proposal. queries raised for compliance.
|
|
18
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
20/09/2018
|
The correction have been made as per the instruction received
|
|
19
|
Nodal Officer
|
EDS
|
CF (CCF Wildlife Jharkhand)
|
26/10/2018
|
Please take note on query raised by Nodal Officer.
|
|
20
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
26/10/2018
|
Please take note on query raised by Nodal Officer.
|
|
21
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
30/10/2018
|
Please take note on queries raised by Nodal Officer
|
|
22
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
05/11/2018
|
correction have been made as per the instruction received
|
|
23
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
07/12/2018
|
Incomplete compliance report of query raised by Nodal Officer
|
|
24
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (dfcc.kolkata@gmail.com)
|
15/12/2018
|
Compliance report Point of 1 -ii and point 2
|
|
25
|
User Agency (dfcc.kolkata@gmail.com)
|
REPLY
|
DFO (Hazaribagh West)
|
17/12/2018
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
20/12/2018
|
Correction have been made as per the instruction received
|
|
27
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
24/12/2018
|
Compliance report of query raised by Nodal Officer
|
|
28
|
CF (CCF Wildlife Jharkhand)
|
REPLY
|
Nodal Officer
|
12/02/2019
|
EDS raised by Nodal Office dated 25.10.2018 reply
|
|