Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bokaro)
|
EDS
|
User Agency (niraj.kumar@gail.co.in)
|
16/07/2022
|
Letter no. 1980 Dt. 16.07.2022 has been uploaded.
|
|
2
|
User Agency (niraj.kumar@gail.co.in)
|
REPLY
|
DFO (Bokaro)
|
21/07/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bokaro)
|
EDS
|
User Agency (niraj.kumar@gail.co.in)
|
08/09/2022
|
Letter no. 2517 Dt 08.09.2017 has been uploaded.
|
|
4
|
User Agency (niraj.kumar@gail.co.in)
|
REPLY
|
DFO (Bokaro)
|
14/09/2022
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
17/11/2022
|
Please refer the attached pdf file regarding essential details sought by Nodal Office.
|
|
6
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
18/11/2022
|
It is requested that the compliance report should be submitted soon after removing the above errors, so that the compliance report can be sent from this office.
|
|
7
|
DFO (Bokaro)
|
EDS
|
User Agency (niraj.kumar@gail.co.in)
|
19/11/2022
|
Memo no. 3226 Dt 18.11.2022 has been attached.
|
|
8
|
User Agency (niraj.kumar@gail.co.in)
|
REPLY
|
DFO (Bokaro)
|
08/12/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
21/12/2022
|
Letter no. 3515 Dt. 21.12.2022 has been attached.
|
|
10
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
06/01/2023
|
Compliance has been done.
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
17/02/2023
|
FRA Certificate with records of meetings held and Comment of CWLW has been sought.
|
|
12
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
27/02/2023
|
Please take note on EDS by Nodal office
|
|
13
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
28/02/2023
|
It is requested that it should be ensured to submit the desired report as soon as possible, so that further action can be taken.
|
|
14
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
01/03/2023
|
Letter no. 592 Dated 01.03.2023 has been attached.
|
|
15
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
02/03/2023
|
Compliance has been done.
|
|
16
|
Nodal Officer
|
REPLY
|
State secretary
|
10/03/2023
|
EDS Reply
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
29/03/2023
|
Kindly fulfill all the decision made by committee members in REC meeting.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
03/04/2023
|
Reply of query raised by REC 60th meeting dated 27.03.2023 has been sought.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
05/04/2023
|
Please take note on EDS by IRO, Ranchi
|
|
20
|
CF (Bokaro)
|
EDS
|
DFO (Bokaro)
|
06/04/2023
|
Please submit the desired report as soon as possible, so that further action can be taken..
|
|
21
|
DFO (Bokaro)
|
EDS
|
User Agency (niraj.kumar@gail.co.in)
|
06/04/2023
|
Please submit the desired report as soon as possible, so that further action can be taken..
|
|
22
|
User Agency (niraj.kumar@gail.co.in)
|
REPLY
|
DFO (Bokaro)
|
06/04/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Bokaro)
|
REPLY
|
CF (Bokaro)
|
10/04/2023
|
Letter no. 926 Dated 08.04.2023 has been attached.
|
|
24
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
12/04/2023
|
Compliance has been done.
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
18/04/2023
|
EDS Reply
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
24/04/2023
|
Reply of query raised by REC, GoI letter dated-27.03.2023 is being submitted.
|
|