Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ramgarh)
|
EDS
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
04/06/2019
|
Hard copy of the said proposal is not submitted in this division till the date.
|
|
2
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
REPLY
|
DFO (Ramgarh)
|
03/03/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Ramgarh)
|
EDS
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
04/03/2020
|
Hard copy of proposal is not submitted by UA
|
|
4
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
REPLY
|
DFO (Ramgarh)
|
25/08/2021
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
03/11/2021
|
Please take note on EDS by Nodal office.
|
|
6
|
CF (Bokaro)
|
EDS
|
DFO (Ramgarh)
|
17/11/2021
|
It should be kindly made available in this office without delay and redressal of the above shortcomings/errors, so that the proposal can be forwarded to the State Government for Stage-I.
|
|
7
|
DFO (Ramgarh)
|
EDS
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
18/11/2021
|
Letter is being enclosed.
|
|
8
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
REPLY
|
DFO (Ramgarh)
|
17/01/2023
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Ramgarh)
|
EDS
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
13/04/2023
|
Letter is being enclosed.
|
|
10
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
REPLY
|
DFO (Ramgarh)
|
13/06/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Ramgarh)
|
EDS
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
16/06/2023
|
Letter is being attached
|
|
12
|
User Agency (sp-ramgarh@jhpolice.gov.in)
|
REPLY
|
DFO (Ramgarh)
|
22/07/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Ramgarh)
|
REPLY
|
CF (Bokaro)
|
02/08/2023
|
correction has been done as per direction.
|
|
14
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
04/08/2023
|
Correction has been done as per direction.
|
|