Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
03/04/2019
|
Letter is enclosed
|
|
2
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
31/05/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
04/06/2019
|
Hard copy is not submitted in this division till the date.
|
|
4
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
11/06/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
18/06/2019
|
Hard copy of compliance is not submitted in this division till the date.
|
|
6
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
21/06/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
12/07/2019
|
Letter is enclosed
|
|
8
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
06/08/2019
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
16/08/2019
|
Compliance of EDS is not submitted in this division
|
|
10
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
26/11/2019
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
11/01/2020
|
CA Land details, KML File, Geo-reference map, Topo sheet map, Land suitability and CA Scheme has not been submitted yet.
|
|
12
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
07/08/2021
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
11/08/2021
|
Letter is being enclosed.
|
|
14
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
07/09/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
08/09/2021
|
No Response has been submitted in response to our letter no 1254 dated 11-08-21.
|
|
16
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
16/11/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
18/11/2021
|
Hard copy of EDS compliance is not submitted.
|
|
18
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
23/11/2021
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
27/11/2021
|
letter is being enclosed
|
|
20
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
04/12/2021
|
The correction have been made as per the instruction received
|
|
21
|
CF (Bokaro)
|
EDS
|
DFO (Ramgarh)
|
21/01/2022
|
On 19.01.2022 during site inspection it was informed that the forests of Kotre, Basantpur and Pachmo mouza are frequently visited by elephant herds. But these are no mention of this fact in the Part-II Sl.No.-7 xi of the proposal. Please specify this fact in Part-II.
|
|
22
|
DFO (Ramgarh)
|
REPLY
|
CF (Bokaro)
|
21/01/2022
|
Data has been updated in Part-II Sl.No-8(i)
|
|
23
|
CF (Bokaro)
|
EDS
|
DFO (Ramgarh)
|
21/01/2022
|
In the online Part-II, Sl.No.-13 i, details of Compensatory Afforestation site at Sl.No.-10, area of Majhladih P.F. is written as 55.83 ha. Whereas the area of Majhladih P.F. is 35.83 ha. in the Land Suitability Certificate of DFO, Giridih East. At Sl.No.-20, Name of P.F. is written as Baraibad whereas it is Badiabad in the Land Suitability Certificate of DFO, Giridih East. Please correct and comply.
|
|
24
|
DFO (Ramgarh)
|
REPLY
|
CF (Bokaro)
|
22/01/2022
|
Data has been updated in Para-13(i) of Part-II
|
|
25
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
04/02/2022
|
Please take note on EDS by Nodal Office
|
|
26
|
CF (Bokaro)
|
EDS
|
DFO (Ramgarh)
|
07/02/2022
|
An EDS has been raised vide the nodal officer's letter no 107 dated 04.02.2022 on 4 points about the project proposal. The letter is also sent to DFO Ramgarh. Please submit compliance on the above so that it can be submitted to the Nodal Officer
|
|
27
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
08/02/2022
|
Letter is being enclosed
|
|
28
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
23/02/2022
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Ramgarh)
|
REPLY
|
CF (Bokaro)
|
28/02/2022
|
The correction has been made as per direction.
|
|
30
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
03/03/2022
|
EDS raised on 4 points by ED Nodal have been complied by the UA Compliance submitted by DFO, Ramgarh has been sent through RCCF, Bokaro.
|
|
31
|
Head Office
|
EDS
|
State secretary
|
23/06/2022
|
eds
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
06/07/2022
|
Reply of query raised by GoI letter dated-22.06.2022 has been sought.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
07/07/2022
|
Please take note on EDS by GOI
|
|
34
|
CF (Bokaro)
|
EDS
|
DFO (Ramgarh)
|
11/07/2022
|
It should be ensured to provide the desired resolution report at the earliest, so that further action can be taken.
|
|
35
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
12/07/2022
|
Letter is being enclosed
|
|
36
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
28/07/2022
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
16/08/2022
|
As per the instruction given by RCCF Bokaro compliance has not been submitted by UA
|
|
38
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
18/08/2022
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Ramgarh)
|
REPLY
|
CF (Bokaro)
|
24/08/2022
|
Compliance has been submitted by UA.
|
|
40
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
30/08/2022
|
Compliance has been done.
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
08/09/2022
|
EDS Reply
|
|
42
|
State secretary
|
REPLY
|
Head Office
|
30/09/2022
|
Reply of query raised by GoI letter dated 22.06.2022 being submitted.
|
|
43
|
Head Office
|
EDS
|
State secretary
|
05/12/2022
|
EDS
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
16/01/2023
|
Neccessary action to be taken regarding GoI letter dated 01.12.2022.
|
|
45
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
24/01/2023
|
Please take note on EDS by Head Office.
|
|
46
|
CF (Bokaro)
|
EDS
|
DFO (Ramgarh)
|
03/02/2023
|
Please take note on EDS by ED Nodal Office, Ranchi.
|
|
47
|
DFO (Ramgarh)
|
REPLY
|
CF (Bokaro)
|
25/02/2023
|
Compliance has been done as per instruction received.
|
|
48
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
28/02/2023
|
Compliance has been done as per instruction received from MoEF&CC, New Delhi.
|
|
49
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
03/03/2023
|
Please take note on EDS
|
|
50
|
CF (Bokaro)
|
EDS
|
DFO (Ramgarh)
|
06/03/2023
|
Please submit compliance report.
|
|
51
|
DFO (Ramgarh)
|
EDS
|
User Agency (pokbp2018@yahoo.com)
|
14/03/2023
|
Letter is being enclosed.
|
|
52
|
User Agency (pokbp2018@yahoo.com)
|
REPLY
|
DFO (Ramgarh)
|
19/05/2023
|
The correction have been made as per the instruction received
|
|
53
|
DFO (Ramgarh)
|
REPLY
|
CF (Bokaro)
|
20/05/2023
|
Compliance report is being submitted.
|
|
54
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
22/05/2023
|
Compliance has been done.
|
|
55
|
Nodal Officer
|
REPLY
|
State secretary
|
23/05/2023
|
EDS raised by MoEF&CC regarding submission of Site Inspection Report of Kotre Basantpur Pachmo OCP (633.19 ha) has been submitted by IRO, Ranchi to MoEF&CC. FAC has accorded Stage - I approval to the proposal in its meeting held on 27.01.2023. Therefore, it is requested to forward the proposal to MoEF&CC for updating the Stage - I status on Parivesh Protal so that necessary compliance can be submitted by User Agency.
|
|
56
|
State secretary
|
REPLY
|
Head Office
|
02/06/2023
|
EDS raised by MoEF&CC regarding site visit by FAC. Report of committee must have been submitted direct by MoEF&CC. MoEF&CC has accorded Stage-I approval on 27.02.2023. Therefore, it is requested to update Stage-I status on Parivesh Portal so that necessary compliance can be submitted by the user agency.
|
|