| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
20/12/2017
|
1. Most of the documents are not duly signed by authorized officer with stamp bearing name of the officer.
2. Some Paras need clarification.
3. Some Paras need rectification. Details are attached.
|
|
|
2
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
30/01/2018
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
07/04/2018
|
1. Upload Geo-reference map in shape file of the forest & J.J. Land which is to be transferred because you have not uploaded it till yet.
2. Upload certificate issued by DC, Chatra regarding FRA 2006.
|
|
|
4
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
27/08/2018
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Ranchi)
|
EDS
|
User Agency (envccl@yahoo.com)
|
22/09/2018
|
please submit the revised land use plan including change in land use . the CA land has been identified by this office . please get the DGPS of this CA land done. also submit FRA and NOC for JJ as soon as possible .
|
|
|
6
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Ranchi)
|
17/11/2020
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
31/12/2020
|
Vide this office letter no. 2789 dated 17.08.2019, the user agency was requested to please fix temporary pillars at the site of the forest land to be diverted. But the same is still undone even after many reminders. Due to which the site inspection this not been done. You are again requested to please fix the temporary pillars at the site.
|
|
|
8
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
27/04/2021
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
02/08/2021
|
In the light of the instruction, received from Nodal Officer, the User Agency has been asked vide D.F.O, Letter No. 1946 dated 02.08.2021 to upload the manual Part-I duly, named, signed and stamped in respect of the undertaking for Payment of C.A. and N.P.V, as additional document and for compliance the proposal in online mode and its hard copy has been returned to the user agency.
|
|
|
10
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
30/08/2021
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Ranchi)
|
EDS
|
User Agency (envccl@yahoo.com)
|
31/08/2021
|
Please fill part 1 and upload it as additional document
|
|
|
12
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Ranchi)
|
11/12/2021
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
04/03/2022
|
The proposal was examined and found deficient is many respects as the requisite documents have not been furnished either online or offline. A request for the same has been sent to the user agency vide DFO letter no. 424 dated 04.03.2022. The compliance is awaited from the user agency for further action at DFO level.
|
|
|
14
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
23/06/2022
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Ranchi)
|
EDS
|
User Agency (envccl@yahoo.com)
|
02/07/2022
|
Please fill Part 1 and upload
|
|
|
16
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Ranchi)
|
26/07/2022
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
27/08/2022
|
The proposal was examined and many shortcomings as well as defects have been found and observed in the proposal as submitted by the user agency and therefore a list of 12 such shortcomings and defects have been prepared and sent to the user agency for rectification and compliance vide DFO letter No. 1830 dated 27.08.2022
|
|
|
18
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
08/02/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
10/03/2023
|
The proposal was examined and many shortcomings as well as defects have been found and observed in the proposal as submitted by the user agency and therefore a list of 12 such shortcomings and defects have been prepared and sent to the user agency for rectification and compliance vide DFO letter No. 1830 dated 27.08.2022
|
|
|
20
|
DFO (Ranchi)
|
EDS
|
User Agency (envccl@yahoo.com)
|
15/05/2023
|
Please compliance as letter attached and also upload hard copy of part 1
|
|
|
21
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
08/09/2023
|
The correction have been made as per the instruction received
|
|
|
22
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Ranchi)
|
08/09/2023
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
28/10/2023
|
The proposal was examined and many shortcomings as well as defects have been found and observed in the proposal as submitted by the user agency and therefore a list of 12 such shortcomings and defects have been prepared and sent to the user agency for rectification and compliance vide DFO letter No. 1830 dated 27.08.2022
|
|
|
24
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
07/02/2024
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
22/02/2024
|
Please upload the Cost benefit Analysis calculated at current NPV rates
|
|
|
26
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
06/03/2024
|
The correction have been made as per the instruction received
|
|
|
27
|
CF (Ranchi)
|
EDS
|
DFO (Ranchi)
|
15/01/2025
|
Compliance of a few conditions of Stage I & II of 312.76Ha proposal is yet to be complied, So the existing proposal of 281.17Ha will be considered after the requisite compliance is done.
|
|
|
28
|
DFO (Ranchi)
|
EDS
|
User Agency (envccl@yahoo.com)
|
18/01/2025
|
Please compliance as letter attached.
|
|
|
29
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Ranchi)
|
22/01/2025
|
The correction have been made as per the instruction received
|
|
|
30
|
DFO (Ranchi)
|
REPLY
|
CF (Ranchi)
|
27/01/2025
|
The correction have been made by user agency as per the instruction received.
|
|
|
31
|
CF (Ranchi)
|
EDS
|
DFO (Ranchi)
|
28/02/2025
|
The proposal is reverted for recording observations on elephant movement in the area of diversion and surrounding mining cluster. It is observed that there is seasonal movement of elephants from Hazaribagh west division to latehar division passing through Tandwa in Chatra South Division and the Churi area in Ranchi division. The elephants use the river beds and remanent patches of green cover in the mining area. There is a need to provide a safe passage for elephants. In the light of the observations the proposal may be reexamined and the possibility of identifying the ecological corridor and its enrichment may be suggested. The possibility of wildlife management plan,habitat management,conflict resolution ,etc may be suggested in the recommendations and other observations may also be high
|
|
|
32
|
DFO (Ranchi)
|
REPLY
|
CF (Ranchi)
|
12/04/2025
|
Data of elephant movement,conflicts resulting in injury/death of human or property loss within 10 km radius of proposed land for the project has been updated.
|
|
|
33
|
CF (Ranchi)
|
EDS
|
DFO (Ranchi)
|
23/04/2025
|
Please include the Wildlife Mgmt. Plan necessity in Recommendation part of the proposal so that it gets incorporated as a condition in its Stage-I.
|
|
|
34
|
DFO (Ranchi)
|
REPLY
|
CF (Ranchi)
|
30/04/2025
|
correction have been made as per the instruction received
|
|
|
35
|
Nodal Officer
|
EDS
|
CF (Chatra)
|
19/06/2025
|
Please take note on EDS by Nodal Officer
|
|
|
36
|
Nodal Officer
|
EDS
|
CF (Ranchi)
|
19/06/2025
|
Please take note on EDS by Nodal Officer
|
|
|
37
|
CF (Ranchi)
|
REPLY
|
Nodal Officer
|
03/07/2025
|
Proposal already sent to Addl. PCCF, Ranchi Region, Ranchi via ltr No- 519 dated 24-05-2025
|
|
|
38
|
CF (Chatra)
|
REPLY
|
Nodal Officer
|
23/07/2025
|
This query in not related to this circle
|
|
|
39
|
Nodal Officer
|
EDS
|
CF (Chatra)
|
29/10/2025
|
Please take note on EDS by Nodal Office
|
|
|
40
|
Nodal Officer
|
EDS
|
CF (Ranchi)
|
29/10/2025
|
Please take note on EDS by Nodal Office
|
|
|
41
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
31/10/2025
|
Please take note on EDS by Nodal Office
|
|
|
42
|
DFO (Chatra South)
|
EDS
|
User Agency (envccl@yahoo.com)
|
07/11/2025
|
Please submit the reply of all queries raised by E.D Nodal vide memo no-829 dated-21-10-2025
|
|
|
43
|
User Agency (envccl@yahoo.com)
|
REPLY
|
DFO (Chatra South)
|
24/02/2026
|
The correction have been made as per the instruction received
|
|
|
44
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
10/03/2026
|
Forwarding letter is being uploaded for further action.
|
|