| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
14/12/2022
|
Please take note on EDS by Nodal Office.
|
|
|
2
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
22/12/2022
|
Please take note on DFO by CF.
|
|
|
3
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
02/01/2023
|
Do necessary action.
|
|
|
4
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
10/01/2023
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
21/01/2023
|
EDC Compliance
|
|
|
6
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
16/03/2023
|
Please take note on DFO by CF.
|
|
|
7
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
08/04/2023
|
Compliance of letter No.321 dt. 10-02-2023
|
|
|
8
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
18/05/2023
|
Under the Forest (Conservation) Act, 1980, M/s Hindalco Industries Limited submitted a redressal report to the Divisional Forest Officer, Lohardaga for the diversion of 7.52 hectares of forest land for bauxite mining in Mauza-Bagdu, Bhusad and Hisari under Lohardaga Forest Division.
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
05/06/2023
|
Please take note on EDS by Nodal office
|
|
|
10
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
06/06/2023
|
Please take note by DFO
|
|
|
11
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
07/06/2023
|
Please upload correct KML file.
|
|
|
12
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
07/06/2023
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
08/06/2023
|
Compliance attached herewith.
|
|
|
14
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
08/06/2023
|
Please take note by DFO
|
|
|
15
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
08/06/2023
|
EDS Compliance attached herewith.
|
|
|
16
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
16/06/2023
|
Please take note by DFO
|
|
|
17
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
16/06/2023
|
Correction of forest area to be diverted was mentioned in same place of Part - I as 7.69 ha. instead of 7.52 ha. carry on suitable correction in difference of proposed area.
|
|
|
18
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
16/06/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
17/06/2023
|
EDS sought by user agency's are enclosed herewith.
|
|
|
20
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
26/06/2023
|
EDS sought by User Agency's are enclosed herewith.
|
|
|
21
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
07/08/2023
|
Please take note on EDS by Nodal Office
|
|
|
22
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
22/08/2023
|
Please take note by DFO
|
|
|
23
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
28/08/2023
|
please upload compliance of EDS raised by PCCF, ED, Jharkhand Ranchi
|
|
|
24
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
28/08/2023
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
30/08/2023
|
The objection raised by PCCF ED Jharkhand Ranchi has been resolved by the user agency as per the instructions, a copy of the same is attached.
|
|
|
26
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
05/09/2023
|
User Agency is EDS has been raised on Parivesh Portal.
|
|
|
27
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
15/09/2023
|
Please take note on EDS by Nodal Office
|
|
|
28
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
23/09/2023
|
Please take note by DFO
|
|
|
29
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
26/12/2023
|
Please upload revised proposal with including C.A. land for safety zone area also.
|
|
|
30
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
20/01/2024
|
The correction have been made as per the instruction received
|
|
|
31
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
04/03/2024
|
Please upload revised proposal with including C.A. land for safety zone area also and submit revised hard copy of proposal offline to this office.
|
|
|
32
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
11/03/2024
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
15/03/2024
|
Please upload Georeferenced DGPS Map of Bagru Mines including area of safety zone, also submit the hard copy of DGPS Map.
|
|
|
34
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
15/03/2024
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
08/04/2024
|
EDS soughted by leter no. 2020 dt. 21-09-23 has been resolved through this office letter no. 715 dated 15-03-2024 (letter attached herewith)
|
|
|
36
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
05/06/2024
|
The Proposed mining site was inspected on 15-03-2024 in the presence of Divisional Forest Officer, Forester and Forest Guards of Lohardaga Forest Division and the representative of Hindalco Indusrties Limited. The proposed site for Bagru Bauxite Mine in inside Bagru, Bhusar and Hisri Protected forests.
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
21/06/2024
|
Please take note on EDS by Nodal Office
|
|
|
38
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
21/06/2024
|
Please take note on DFO by CF.
|
|
|
39
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
21/06/2024
|
Please take note and take necessary action.
|
|
|
40
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
28/06/2024
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
28/06/2024
|
Working plan prescription uploaded
|
|
|
42
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
02/08/2024
|
Working Plan Prescription uploaded.
|
|
|
43
|
State secretary
|
EDS
|
Nodal Officer
|
18/10/2024
|
Comment of CWLW
|
|
|
44
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
05/11/2024
|
Please take note on EDS by GOJ
|
|
|
45
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
09/12/2024
|
Please take note by DFO
|
|
|
46
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
19/12/2024
|
EDS reply has been done, plese see in the attachment.
|
|
|
47
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
27/12/2024
|
EDS reply has been done,
|
|
|
48
|
Nodal Officer
|
REPLY
|
State secretary
|
16/01/2025
|
EDS Reply
|
|
|
49
|
State secretary
|
EDS
|
Nodal Officer
|
06/02/2025
|
Reply of query raised by letter dated-05.02.2025 has been sought.
|
|
|
50
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
06/03/2025
|
Please take note on EDS by GOJ
|
|
|
51
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
08/03/2025
|
Please take note by DFO
|
|
|
52
|
Nodal Officer
|
EDS
|
CF (Gumla)
|
12/03/2025
|
Please take note on EDS by Nodal Office
|
|
|
53
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
12/03/2025
|
Please take note by DFO
|
|
|
54
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
27/03/2025
|
EDS Resovled
|
|
|
55
|
CF (Gumla)
|
EDS
|
DFO (Lohardaga)
|
03/05/2025
|
Out of total forest area of 19.56 Ha , apart from forest diversion area the area under infrastructures also needs diversion? What recent FC Guidelines says
|
|
|
56
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
12/08/2025
|
Broken area not submitted.
|
|
|
57
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
25/09/2025
|
The correction have been made as per the instruction received
|
|
|
58
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
25/09/2025
|
On your request , the proposal is being returned for correctio.
|
|
|
59
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
10/10/2025
|
The correction have been made as per the instruction received
|
|
|
60
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
16/10/2025
|
On your request , the proposal is being returned for correction.
|
|
|
61
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
30/10/2025
|
The correction have been made as per the instruction received
|
|
|
62
|
DFO (Lohardaga)
|
EDS
|
User Agency (basudev1965@gmail.com)
|
15/12/2025
|
Please provide complete details of project diversion area breakup under project details.
|
|
|
63
|
User Agency (basudev1965@gmail.com)
|
REPLY
|
DFO (Lohardaga)
|
22/12/2025
|
The correction have been made as per the instruction received
|
|
|
64
|
DFO (Lohardaga)
|
REPLY
|
CF (Gumla)
|
09/01/2026
|
The correction have been made as per th instruction received.
|
|
|
65
|
CF (Gumla)
|
REPLY
|
Nodal Officer
|
28/01/2026
|
As the forest land proposed for diversion is part of approved mining lease area and the availability of bauxite ore is site specific the proposal may be accepted.
|
|
|
66
|
Nodal Officer
|
REPLY
|
State secretary
|
17/02/2026
|
EDS Reply
|
|