  (i). Proposal No. : FP/JH/IRRIG/23840/2017              (ii). Name of Project for which Forest Land is required : North Koel Reservoir Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The present proposal is for the diversion of forest land for North Koel Reservoir Project. The project was conceived in 1960s by the Govt. of Bihar and the project was started in 1970s. It was envisaged to construct a masonry Dam on North Koel River nearKutku village under Barwadih Block of Latehat              (iv). State : Jharkhand              (v). Category of the Project : Irrigation              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 1007.29
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR)Stage-I Approval onStage-II Approval on
FP/JH/IRRIG/23840/201731/01/201731/01/2017  31/01/2017   03/02/2017  31/01/2017   03/02/2017   07/02/2017 Latehar :08/02/2017Medininagar:
  22/04/2017 (Latehar)

  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by Circle (Medininagar) on:24/08/2017  
Query raised by DFO (Latehar) on:31/08/2018  
Replied by UA on :27/04/2022  
NOTE:- Proposal is pending at DFO due to EDS raised by CF .