TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/IND/33374/2018              (ii). Name of Project for which Forest Land is required : Hindustan Petroleum Corporation Limited              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : expansion of existing LPG bottling plant for the storage of the product. Mounded storage vessel with in the existing boundary of the alloted land by AIADA jAMSHEDPUR.JHARKHAND.              (iv). State : Jharkhand              (v). Category of the Project : Industry              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 8.74
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JH/IND/33374/201804/05/201804/01/2019  28/12/2018  25/07/2018  28/05/2018   24/01/2019  02/01/2019  21/12/2018  19/07/2018   31/01/2019   11/02/2019 Saraikela :13/02/2019Jamshedpur:
  24/08/2019 (Saraikela)

Jharkhand:
29/08/2019
Jharkhand:
13/09/2019
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Jharkhand) on:18/10/2019  
Query raised by Nodal Officer (Jharkhand) on:05/11/2019  
Replied by Circle(Jamshedpur) on:05/01/2023  
Query raised by Nodal Officer (Jharkhand) on:23/03/2023  
Replied by Circle() on:  
Query raised by Circle (Jamshedpur) on:09/09/2021  
Replied by DFO (Saraikela) on:23/12/2022  
Query raised by Circle (Jamshedpur) on:19/04/2023  
Replied by DFO () on:  
Query raised by DFO (Saraikela) on:31/03/2019  
Replied by UA on :10/04/2019  
Query raised by DFO (Saraikela) on:10/05/2019  
Replied by UA on :07/06/2019  
Query raised by DFO (Saraikela) on:26/06/2019  
Replied by UA on :26/07/2019  
Query raised by DFO (Saraikela) on:14/08/2019  
Replied by UA on :22/08/2019  
Query raised by DFO (Saraikela) on:22/08/2019  
Replied by UA on :24/08/2019  
NOTE:- Proposal is pending at DFO due to EDS raised by State Government .