Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Medininagar)
|
EDS
|
User Agency (dfo-ptrsouth@gov.in)
|
01/10/2020
|
Please submit hard copy of proposal.
|
|
2
|
User Agency (dfo-ptrsouth@gov.in)
|
REPLY
|
DFO (Medininagar)
|
01/10/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Medininagar)
|
EDS
|
User Agency (dfo-ptrsouth@gov.in)
|
09/10/2020
|
Sir please see the attachment file.
|
|
4
|
User Agency (dfo-ptrsouth@gov.in)
|
REPLY
|
DFO (Medininagar)
|
31/03/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Medininagar)
|
EDS
|
User Agency (dfo-ptrsouth@gov.in)
|
01/06/2021
|
Sir please see the attachment file.
|
|
6
|
User Agency (dfo-ptrsouth@gov.in)
|
REPLY
|
DFO (Medininagar)
|
10/08/2021
|
The correction have been made as per the instruction received
|
|
7
|
CF (Medininagar)
|
EDS
|
DFO (Medininagar)
|
31/08/2021
|
part 1 and 2 must be submitted in the new formate provided by office of PCCF ED
|
|
8
|
DFO (Medininagar)
|
EDS
|
User Agency (dfo-ptrsouth@gov.in)
|
31/08/2021
|
part 1 and 2 must be submitted in the new formate provided by office of PCCF ED
|
|
9
|
User Agency (dfo-ptrsouth@gov.in)
|
REPLY
|
DFO (Medininagar)
|
31/08/2021
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Medininagar)
|
REPLY
|
CF (Medininagar)
|
01/09/2021
|
Query Complied
|
|
11
|
Nodal Officer
|
EDS
|
CF (Medininagar)
|
23/09/2021
|
Please take note on EDS by Nodal officer
|
|
12
|
CF (Medininagar)
|
REPLY
|
Nodal Officer
|
27/09/2021
|
Sir,
Please see letter No. 1265 dated 27.09.2021
|
|
13
|
Head Office
|
EDS
|
State secretary
|
21/02/2022
|
eds
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
04/03/2022
|
Reply of query raised GoI, New Delhi letter dated-16.02.2022 has been sought
|
|
15
|
Nodal Officer
|
EDS
|
CF (Medininagar)
|
07/03/2022
|
Please take note on EDS by GOI
|
|
16
|
CF (Medininagar)
|
EDS
|
DFO (Medininagar)
|
08/03/2022
|
Please take note on EDS by GOI
|
|
17
|
DFO (Medininagar)
|
EDS
|
User Agency (dfo-ptrsouth@gov.in)
|
08/03/2022
|
Please take note on EDS by GOI
|
|
18
|
User Agency (dfo-ptrsouth@gov.in)
|
REPLY
|
DFO (Medininagar)
|
06/04/2022
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Medininagar)
|
EDS
|
User Agency (dfo-ptrsouth@gov.in)
|
11/04/2022
|
On request of User Agency by Letter No.- 363, Dated- 11-04-2022 the reply of query has been sent back to User Agency for necessary action.
|
|
20
|
User Agency (dfo-ptrsouth@gov.in)
|
REPLY
|
DFO (Medininagar)
|
11/04/2022
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Medininagar)
|
REPLY
|
CF (Medininagar)
|
19/04/2022
|
Sir, Please see the attachment file.
|
|
22
|
CF (Medininagar)
|
REPLY
|
Nodal Officer
|
21/04/2022
|
Sir,
Please see the attachment file.
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
20/05/2022
|
Reply of Query raised has been forwarded vide ED's letter no.394 dated 09.05.2022.
|
|
24
|
State secretary
|
REPLY
|
Head Office
|
09/06/2022
|
Reply of query raised by GoI letter dated 16.02.2022 being submitted.
|
|
25
|
Head Office
|
EDS
|
State secretary
|
12/07/2022
|
eds
|
|
26
|
State secretary
|
REPLY
|
Head Office
|
18/08/2022
|
Reply of query raised by GoI letter dated 07.07.2022 being submitted.
|
|
27
|
Head Office
|
EDS
|
State secretary
|
31/10/2022
|
eds
|
|
28
|
State secretary
|
REPLY
|
Head Office
|
22/11/2022
|
Reply of EDS is being submitted.
|
|