TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/ENCRH/39652/2019              (ii). Name of Project for which Forest Land is required : ALOKE STEELS INDUSTRIES PVT LTD              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Expansion of existing DRI plant (4 X 100 tpd kiln) by adding the captive power plant and SMS for capacity expansion and to control the pollution.              (iv). State : Jharkhand              (v). Category of the Project : Encroachments              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 9.27
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onStage-II Approval on
FP/JH/ENCRH/39652/201901/04/201907/08/2019  16/07/2019  11/07/2019  14/06/2019  03/04/2019   08/08/2019  28/07/2019  12/07/2019  01/07/2019  12/06/2019   01/08/2019   02/08/2019 Ramgarh :20/08/2019Bokaro:
  14/11/2023 (Ramgarh)

Jharkhand:
12/12/2023
Jharkhand:
13/01/2024
Ranchi:
04/03/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:24/07/2024  
Replied by State Government(Jharkhand) on:05/11/2024  
Query raised by Regional Office (Ranchi) on:04/12/2024  
Query raised by State Government (Jharkhand) on:07/01/2025  
Replied by Nodal Officer (Jharkhand) on:07/10/2025  
Query raised by Nodal Officer (Jharkhand) on:15/01/2025  
Replied by Circle(Bokaro) on:21/03/2025  
Query raised by Nodal Officer (Jharkhand) on:23/04/2025  
Replied by Circle(Bokaro) on:18/08/2025  
Query raised by Circle (Bokaro) on:20/01/2025  
Replied by DFO (Ramgarh) on:08/03/2025  
Query raised by Circle (Bokaro) on:29/04/2025  
Replied by DFO (Ramgarh) on:11/06/2025  
Query raised by Circle (Bokaro) on:23/06/2025  
Replied by DFO (Ramgarh) on:10/07/2025  
Query raised by DFO (Ramgarh) on:20/08/2019  
Replied by UA on :19/07/2023  
Query raised by DFO (Ramgarh) on:05/08/2023  
Replied by UA on :17/08/2023  
Query raised by DFO (Ramgarh) on:30/08/2023  
Replied by UA on :02/09/2023  
Query raised by DFO (Ramgarh) on:14/09/2023  
Replied by UA on :26/09/2023  
Query raised by DFO (Ramgarh) on:27/09/2023  
Replied by UA on :28/09/2023  
Query raised by DFO (Ramgarh) on:11/10/2023  
Replied by UA on :12/10/2023  
Query raised by DFO (Ramgarh) on:12/10/2023  
Replied by UA on :13/10/2023  
Query raised by DFO (Ramgarh) on:18/10/2023  
Replied by UA on :23/10/2023  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .