Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dumka)
|
EDS
|
User Agency (eengbcddumka-jhr@nic.in)
|
28/12/2017
|
Please submit the required documents
|
|
2
|
User Agency (eengbcddumka-jhr@nic.in)
|
REPLY
|
DFO (Dumka)
|
24/02/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Dumka)
|
EDS
|
User Agency (eengbcddumka-jhr@nic.in)
|
21/03/2018
|
Area of Compensatory Afforestation applied is wrongly. Cadastral Map of Diverted land and Compensatory Afforestation land has not been uploaded
|
|
4
|
User Agency (eengbcddumka-jhr@nic.in)
|
REPLY
|
DFO (Dumka)
|
24/03/2018
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Dumka)
|
26/04/2018
|
Please take note on query raised by Nodal Officer.
|
|
6
|
CF (Dumka)
|
EDS
|
DFO (Dumka)
|
04/05/2018
|
Please reply the query.
|
|
7
|
DFO (Dumka)
|
EDS
|
User Agency (eengbcddumka-jhr@nic.in)
|
04/05/2018
|
Please reply the query
|
|
8
|
User Agency (eengbcddumka-jhr@nic.in)
|
REPLY
|
DFO (Dumka)
|
15/06/2018
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Dumka)
|
REPLY
|
CF (Dumka)
|
15/06/2018
|
Corrections have been made
|
|
10
|
CF (Dumka)
|
REPLY
|
Nodal Officer
|
15/06/2018
|
Corrections have been made
|
|
11
|
Nodal Officer
|
EDS
|
CF (Dumka)
|
28/06/2018
|
Please take note on query raised by Nodal Officer.
|
|
12
|
CF (Dumka)
|
EDS
|
DFO (Dumka)
|
28/06/2018
|
Please take note on query raised by Nodal officer.
|
|
13
|
DFO (Dumka)
|
REPLY
|
CF (Dumka)
|
28/06/2018
|
Query Reply
|
|
14
|
CF (Dumka)
|
REPLY
|
Nodal Officer
|
28/06/2018
|
Query Reply
|
|
15
|
Nodal Officer
|
EDS
|
CF (Dumka)
|
28/06/2018
|
Annexure not attached
|
|
16
|
CF (Dumka)
|
EDS
|
DFO (Dumka)
|
28/06/2018
|
Annexure not uploaded
|
|
17
|
DFO (Dumka)
|
REPLY
|
CF (Dumka)
|
28/06/2018
|
Query Reply
|
|
18
|
CF (Dumka)
|
REPLY
|
Nodal Officer
|
28/06/2018
|
Query Reply.
|
|