TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/WATER/156175/2022              (ii). Name of Project for which Forest Land is required : Laying of canal based water supply for Nimer Badesara Group of 35 nos. villages distt Charkhi Dadri              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of canal based water pipe line alongwith Loharu Canal from Raw water pumping station to Nimer Badesara water works in Sub Division, Badhra under forest division and district Charkhi Dadri, Haryana. The project approved on dated 28.03.2021.              (iv). File no. : 9-HRB144-2023-CHA              (v). State : Haryana              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.891
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/WATER/156175/202205/06/202223/06/2022   04/07/2022   05/07/2022   08/08/2022 Charkhi Dadri :15/09/2022West Circle Hissar:
  03/04/2023 (Charkhi Dadri)

Haryana:
18/04/2023
Haryana:
09/06/2023
Chandigarh:
28/06/2023
29/08/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:29/07/2023  
Replied by State Government(Haryana) on:14/08/2023  
Query raised by State Government (Haryana) on:12/06/2023  
Replied by Nodal Officer (Haryana) on:16/06/2023  
Query raised by State Government (Haryana) on:01/08/2023  
Replied by Nodal Officer (Haryana) on:14/08/2023  
Query raised by Nodal Officer (Haryana) on:04/05/2023  
Replied by Circle(West Circle Hissar) on:12/05/2023  
Query raised by Nodal Officer (Haryana) on:17/05/2023  
Replied by Circle(West Circle Hissar) on:01/06/2023  
Query raised by Nodal Officer (Haryana) on:01/08/2023  
Replied by Circle(West Circle Hissar) on:07/08/2023  
Query raised by Nodal Officer (Haryana) on:08/08/2023  
Replied by Circle(West Circle Hissar) on:10/08/2023  
Query raised by Nodal Officer (Haryana) on:11/08/2023  
Replied by Circle(West Circle Hissar) on:13/08/2023  
Query raised by Circle (West Circle Hissar) on:04/05/2023  
Replied by DFO (Charkhi Dadri) on:12/05/2023  
Query raised by Circle (West Circle Hissar) on:17/05/2023  
Replied by DFO (Charkhi Dadri) on:01/06/2023  
Query raised by Circle (West Circle Hissar) on:02/08/2023  
Replied by DFO (Charkhi Dadri) on:04/08/2023  
Query raised by Circle (West Circle Hissar) on:08/08/2023  
Replied by DFO (Charkhi Dadri) on:09/08/2023  
Query raised by Circle (West Circle Hissar) on:11/08/2023  
Replied by DFO (Charkhi Dadri) on:13/08/2023  
Query raised by DFO (Charkhi Dadri) on:27/12/2022  
Replied by UA on :19/02/2023  
Query raised by DFO (Charkhi Dadri) on:17/03/2023  
Replied by UA on :20/03/2023  
Query raised by DFO (Charkhi Dadri) on:10/05/2023  
Replied by UA on :10/05/2023  
Query raised by DFO (Charkhi Dadri) on:19/05/2023  
Replied by UA on :30/05/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)