TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/TRANS/45123/2020              (ii). Name of Project for which Forest Land is required : Jindal Global City              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Installation of 11 KV Overhead HT electricity cable line for residents, students and professors form india and abroad living in jindal Global City              (iv). File no. : 9-HRB025-2020-CHA              (v). State : Haryana              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.08
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/TRANS/45123/202017/03/202020/03/2020  19/03/2020  18/03/2020   20/03/2020  19/03/2020  18/03/2020   20/03/2020   03/04/2020 Sonipat :03/04/2020Central Circle Rohtak:
  10/04/2020 (Sonipat)

Haryana:
17/04/2020
Haryana:
27/04/2020
Chandigarh:
27/04/2020
15/09/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:15/05/2020  
Replied by State Government(Haryana) on:24/08/2020  
Query raised by State Government (Haryana) on:16/06/2020  
Replied by Nodal Officer (Haryana) on:24/08/2020  
Query raised by Nodal Officer (Haryana) on:17/04/2020  
Replied by Circle(Central Circle Rohtak) on:27/04/2020  
Query raised by Nodal Officer (Haryana) on:16/06/2020  
Replied by Circle(Central Circle Rohtak) on:16/07/2020  
Query raised by Nodal Officer (Haryana) on:27/07/2020  
Replied by Circle(Central Circle Rohtak) on:06/08/2020  
Query raised by Circle (Central Circle Rohtak) on:20/04/2020  
Replied by DFO (Sonipat) on:27/04/2020  
Query raised by Circle (Central Circle Rohtak) on:22/06/2020  
Replied by DFO (Sonipat) on:15/07/2020  
Query raised by Circle (Central Circle Rohtak) on:29/07/2020  
Replied by DFO (Sonipat) on:06/08/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .