TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/TRANS/144364/2021              (ii). Name of Project for which Forest Land is required : Const. of 132 KV DC transmission line from Lula Ahir to Buroli termination and 2nd Buroli to Pali Gothra in district Rewari Haryana.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Const. of 132 KV DC transmission line from Lula Ahir to Buroli termination and 2nd Buroli to Pali Gothra in district Rewari Haryana. The project alreaday approved by Superintending Engineer/Contracts for CE/PD&C, HVPNL, Panchkula vide ltr no. 9 dated 21.09.2020              (iv). File no. : 9-HRB023-2022-CHA              (v). State : Haryana              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.4455
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/TRANS/144364/202104/08/202111/08/2021   12/08/2021   13/08/2021   22/09/2021 Rewari :24/09/2021South Circle Gurgaon:
  14/12/2021 (Rewari)

Haryana:
28/12/2021
Haryana:
03/03/2022
Chandigarh:
03/03/2022
23/03/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Haryana) on:18/01/2022  
Replied by Circle(South Circle Gurgaon) on:03/02/2022  
Query raised by Circle (South Circle Gurgaon) on:18/01/2022  
Replied by DFO (Rewari) on:02/02/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .