| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
16/03/2021
|
Case Down
|
|
|
2
|
CF (West Circle Hissar)
|
EDS
|
DFO (Hisar)
|
18/03/2021
|
Case Down
|
|
|
3
|
DFO (Hisar)
|
EDS
|
User Agency (pwdhisar2017@gmail.com)
|
22/03/2021
|
EDS Raised
|
|
|
4
|
User Agency (pwdhisar2017@gmail.com)
|
REPLY
|
DFO (Hisar)
|
31/03/2021
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Hisar)
|
EDS
|
User Agency (pwdhisar2017@gmail.com)
|
02/04/2021
|
EDS Raised
|
|
|
6
|
User Agency (pwdhisar2017@gmail.com)
|
REPLY
|
DFO (Hisar)
|
12/04/2021
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Hisar)
|
REPLY
|
CF (West Circle Hissar)
|
17/05/2021
|
EDS Removed
|
|
|
8
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
20/05/2021
|
EDS Removed
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
01/06/2021
|
Site inspection report by CCF be uploaded
|
|
|
10
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
01/06/2021
|
Site inspection report by CCF uploaded
|
|