TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/ROAD/48568/2020              (ii). Name of Project for which Forest Land is required : Construction of 6 Lane access controlled Highway from DND- Faridabad-Ballabhgarh Bypass Junction with Delhi-Vadodara Expressway KMP- Interchange (NH-148 NA) under Bharatmala Pariyojana (Lot-4/Pkg-I)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 3.9 Ha of forest land for Construction of 6 Lane access controlled Highway from DND- Faridabad-Ballabhgarh Bypass Junction with Delhi-Vadodara Expressway KMP- Interchange (NH-148 NA) under Bharatmala Pariyojana (Lot-4/Package-1) in state of Haryana              (iv). File no. : 9-HRB076-2021-CHA              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.9
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HR/ROAD/48568/202010/08/202020/08/2020   23/10/2020   23/10/2020   03/11/2020 Faridabad :16/11/2020South Circle Gurgaon:
  27/04/2021 (Faridabad)

Haryana:
29/04/2021
Haryana:
21/05/2021
Chandigarh:
21/05/2021
22/06/2021
By :Regional Office
Haryana
13/06/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Faridabad) on:08/12/2020  
Replied by UA on :15/12/2020  
Query raised by DFO (Faridabad) on:21/12/2020  
Replied by UA on :24/02/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Chandigarh) on:25/07/2024  
Query raised by State Government (Haryana) on:12/08/2024  
Query raised by Nodal Officer on:16/08/2024  
Replied by UA on :15/01/2025  
Query raised by Nodal Officer on:07/04/2025  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .