  (i). Proposal No. : FP/HR/ROAD/42775/2019              (ii). Name of Project for which Forest Land is required : Construction of 2 lane ROB at Bhiwani Hansi Road to Tosham Bye pass              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 2 land ROB at Bhiwani Hansi Road To Tosham Bye pass at Level Crossing No. 54-A under forest division and District Bhiwani Haryana              (iv). File no. : 9-HRB058-2020-CHA              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.812
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HR/ROAD/42775/201907/11/2019aa21/11/2019   02/12/2019 Bhiwani(West Circle Hissar) :09/12/2019West Circle Hissar:
  30/06/2020 (Bhiwani(West Circle Hissar))

Haryana:
06/07/2020
Haryana:
24/07/2020
Chandigarh:
24/07/2020
24/09/2021
By :Regional Office
Haryana
17/05/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:25/08/2020  
Replied by State Government(Haryana) on:18/01/2021  
Query raised by Regional Office (Chandigarh) on:03/02/2021  
Replied by State Government(Haryana) on:17/09/2021  
Query raised by State Government (Haryana) on:17/09/2020  
Replied by Nodal Officer (Haryana) on:18/01/2021  
Query raised by State Government (Haryana) on:25/03/2021  
Replied by Nodal Officer (Haryana) on:17/09/2021  
Query raised by Nodal Officer (Haryana) on:22/07/2020  
Replied by Circle(West Circle Hissar) on:22/07/2020  
Query raised by Nodal Officer (Haryana) on:17/09/2020  
Replied by Circle(West Circle Hissar) on:16/10/2020  
Query raised by Nodal Officer (Haryana) on:17/12/2020  
Replied by Circle(West Circle Hissar) on:06/01/2021  
Query raised by Nodal Officer (Haryana) on:25/03/2021  
Replied by Circle(West Circle Hissar) on:02/09/2021  
Query raised by Circle (West Circle Hissar) on:22/07/2020  
Replied by DFO (Bhiwani(West Circle Hissar)) on:22/07/2020  
Query raised by Circle (West Circle Hissar) on:18/09/2020  
Replied by DFO (Bhiwani(West Circle Hissar)) on:15/10/2020  
Query raised by Circle (West Circle Hissar) on:17/12/2020  
Replied by DFO (Bhiwani(West Circle Hissar)) on:06/01/2021  
Query raised by Circle (West Circle Hissar) on:25/03/2021  
Replied by DFO (Bhiwani(West Circle Hissar)) on:01/09/2021  
Query raised by DFO (Bhiwani(West Circle Hissar)) on:31/12/2019  
Replied by UA on :08/01/2020  
Query raised by DFO (Bhiwani(West Circle Hissar)) on:07/10/2020  
Replied by UA on :07/10/2020  
Query raised by DFO (Bhiwani(West Circle Hissar)) on:11/08/2021  
Replied by UA on :24/08/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Chandigarh) on:26/05/2022  
Query raised by State Government (Haryana) on:31/05/2022  
Query raised by Nodal Officer on:31/05/2022  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .